A framework agreement sets the terms of the public contracts a contracting authority will award under it later. This guide covers its term and parties, the award of contracts with and without a mini-competition, the standstill period, nullity and contesting.

Updated 19 November 2026

Reviewed by Mara Ribeiro Duarte, Head of Public Sector at Closer · 20 November 2026

Legal basis§ 4 cl 15 · § 4 cl 17¹ · § 29(1) · § 23(4) · § 29(2) · § 29(3) · § 83(3) · § 30 · § 30(1) · § 30(2) · § 30(3) · § 30(4) · § 30(5) · § 30(6) · § 30(6) cl 1 · § 30(6) cl 2 · § 30(7) · § 30(8) · § 14(1) · § 30(9) · § 30(9) cl 1 · § 30(9) cl 2 · § 30(9) cl 3 · § 30(9) cl 3¹ · § 30(9) cl 4 · § 85 · § 86 · § 30(10) · § 30(10¹) · § 95(1) · § 95(4) · § 30(10²) · § 30(10⁴) · § 30(10³) · § 96 · § 40(1) · § 40(1) cl 1 · § 40(1) cl 2 · § 40(2) · § 40(3) · § 120(3) · § 30(11) · § 31(1) · § 31(2) · § 197(3) cl 1 · § 197(3) cl 2 · § 185(1) · § 189(5) · official text

What a framework agreement is

A framework agreement is an agreement between one or more contracting authorities or entities and one or more economic operators that sets the terms of the public contracts to be awarded under it during its period of validity (§ 4 cl 15). It is awarded in procurement proceedings like a public contract (§ 4 cl 17¹), and the provisions on public contracts apply to it unless the Act provides otherwise (§ 29(1)).

The estimated value of a framework agreement is the maximum total value of all public contracts expected to be awarded under it during its validity (§ 23(4)).

Concluding the framework agreement

  • Term. A framework agreement may be concluded for up to four years. A longer term is allowed only where it is justified, in particular by the subject matter of the agreement. A framework agreement without a fixed term is prohibited (§ 29(2)).
  • Contracts that outlast it. A public contract awarded under the framework agreement while the agreement is valid may run for a shorter or longer term than the agreement itself (§ 29(3)).
  • Parties. Only contracting authorities or entities identifiable from the procurement documents may award contracts under the agreement, and only to the tenderers with whom the agreement was concluded (§ 30(2)). No other authority and no other tenderer can use the agreement.
  • Reporting. Within 30 days after each 12 months from the conclusion of the agreement, the authority files with the register the dates and values of the contracts awarded under it in that period (§ 83(3)).

Awarding contracts under the agreement

Contracts under a framework agreement are awarded on its terms and under the rules of § 30, without substantially changing the terms of the agreement (§ 30(1)). Which route applies depends on the number of tenderers and on whether the agreement already sets all the terms.

  • One tenderer. The contract is awarded on the terms laid down in the framework agreement. Where needed, the authority may ask the tenderer to supplement its initial tender (§ 30(3)).
  • Several tenderers, not all terms set. The authority holds a mini-competition among the tenderers party to the agreement (§ 30(4)). A mini-competition (in the official English text, a reopening of competition) is a competition among those tenderers, held under the Act and the framework agreement, with the aim of awarding a public contract (§ 30(5)).
  • Several tenderers, all terms set. The authority may choose (§ 30(6)) to award the contract on the terms of the agreement without a mini-competition (§ 30(6) cl 1), or partly on the terms of the agreement and partly on the results of a mini-competition (§ 30(6) cl 2). The second option must be provided for in the procurement documents, with the objective criteria by which the authority decides to hold a mini-competition for a given subject matter or lot, and the documents must say which terms the mini-competition may cover (§ 30(7)).
  • Free choice for small contracts. In a framework agreement that sets all the terms, the authority may provide that it can award a contract to a freely chosen tenderer party to the agreement, provided the total value of such contracts does not exceed 20 per cent of the value of the whole framework agreement and each such contract is below the simple procurement threshold (§ 30(8), § 14(1)).

How a mini-competition is held

The framework agreement sets the rules of the mini-competition, subject to the following conditions (§ 30(9)):

  • Invitation. The authority invites, in a form reproducible in writing, all tenderers party to the agreement that are able to perform the contract (§ 30(9) cl 1).
  • Time limit. It sets a reasonable time limit for tenders, taking account of the complexity of the subject matter and the time needed to tender (§ 30(9) cl 2).
  • Tenders. Tenders are submitted in a form reproducible in writing (§ 30(9) cl 3). Where the estimated value of the contract is at least the simple procurement threshold, tenders are opened only after the time limit has expired (§ 30(9) cl 3¹).
  • Award. The contract goes to the tenderer with the most economically advantageous tender under the award criteria set for the mini-competition in the procurement documents of the framework agreement; those criteria must meet the conditions of § 85 and § 86 (§ 30(9) cl 4).

Additional selection. The procurement documents of the framework agreement may set conditions for further selection of tenderers at the mini-competition. A required minimum annual net turnover may not exceed twice the estimated value of the largest contract to be performed at the same time under the same agreement; where those values are not known, it is calculated from the estimated value of the framework agreement (§ 30(10)).

Exclusion check. Where a Single Procurement Document was used in the proceedings for the framework agreement, the authority checks before awarding a contract on the results of a mini-competition that none of the grounds for exclusion in § 95(1) and § 95(4) applies to the chosen tenderer, and does not award the contract to a tenderer to whom one applies (§ 30(10¹)). The check is mandatory where the estimated value of the contract is at least the international threshold; below it, and for contracts under a single-tenderer agreement or awarded without a mini-competition, as well as where the value of the framework agreement is below the international threshold, the authority may apply it only if the procurement documents provide for it (§ 30(10²), § 30(10⁴)). In the check the authority follows § 96 and does not ask for documents it can obtain from a database without material cost or already holds (§ 30(10³)).

Mini-competitions using electronic catalogues

Where a framework agreement with several tenderers was concluded after tenders were submitted as electronic catalogues, a contracting authority may provide that mini-competitions take place on updated catalogues (§ 40(1)). It either invites the tenderers to resubmit catalogues adapted to the mini-competition (§ 40(1) cl 1) or, if the procurement documents provided for this, collects the information needed from the catalogues already submitted (§ 40(1) cl 2). In the second case it tells each tenderer when it will collect the information, lets them refuse, leaves adequate time (§ 40(2)), and shows each tenderer the information collected before awarding the contract, so that it can object or confirm that the tender contains no material errors (§ 40(3)).

Standstill, voidness and contesting

  • No mandatory standstill. The general standstill period need not be applied to a public contract awarded under a framework agreement (§ 120(3)).
  • Optional notice and seven-day standstill. The authority may make the award decision and notify every tenderer party to the agreement, naming the selected tenderer or tenderers and, for an unselected tenderer, giving the characteristics and advantages of the selected tender compared with its own. The contract is then preceded by a seven-day standstill period from the notification (§ 30(11)).
  • Voidness. A contract awarded under a framework agreement is void where the authority breached the mini-competition conditions of § 30(9), unless it applied the notice and standstill of § 30(11) (§ 31(1)). That voidness can be relied on only once it has been established as the Act provides (§ 31(2)). The Review Committee may establish it or, where significant public interests require, leave the contract in force with a shortened term (§ 197(3) cl 1, § 197(3) cl 2).
  • Contesting. A tenderer may contest the authority's actions with the Review Committee (§ 185(1)). In a procedure for awarding a contract under a framework agreement, the contestation notice must reach the Committee within seven days from the day the contesting party learned or should have learned of the infringement, but not after the contract is concluded (§ 189(5)).

How the value of the framework agreement is calculated is explained in the guide on estimated value; time limits are in the FAQ on time limits and the next steps of a dispute in the guide on contestation. This guide does not cover dynamic purchasing systems, the procedure for concluding the framework agreement itself, or the modification of framework agreements and of contracts awarded under them.