The estimated value decides which rules of the Public Procurement Act apply to a purchase. This guide sets out how the contracting authority calculates it, the special rules for supplies, services, works and concessions, and when a procurement may be divided into lots or into separate procurements.

Updated 19 November 2026

Reviewed by Mara Ribeiro Duarte, Head of Public Sector at Closer · 20 November 2026

Legal basis§ 15(1) · § 15(2) · § 15(11) · § 14(1) cl 1 · § 14(1) cl 2 · § 14(3) · § 23(1) · § 23(2) · § 23(2) cl 1 · § 23(2) cl 2 · § 23(2) cl 5 · § 23(3) · § 23(4) · § 23(5) · § 23(6) · § 23(7) · § 23(8) · § 23(9) · § 24(1) cl 1 · § 24(1) cl 2 · § 24(1) cl 3 · § 24(2) cl 1 · § 24(2) cl 2 · § 24(3) · § 24(4) cl 1 · § 24(4) cl 2 · § 25 · § 26(1) · § 26(2) · § 27(1) · § 27(2) · § 27(3) · § 27(4) · § 27(5) · § 28(1) · § 28(2) · § 28(3) · § 28(4) cl 1 · § 28(4) cl 2 · official text

Why the estimated value matters

The estimated value of the public contract decides which rules the contracting authority must apply. A contract whose estimated value equals or exceeds the simple procurement threshold but remains below the international threshold is awarded under the simple procedure (§ 15(1)); at or above the international threshold the authority applies the rules of Chapter 2 of the Act (§ 15(2)).

  • The simple procurement threshold is 50 000 euros for supplies or services and 100 000 euros for works (§ 14(1) cl 1, § 14(1) cl 2).
  • The international threshold is set by the European Commission (§ 14(3)). For 2026 and 2027 it is 140 000 euros for supplies and services of central government authorities, 216 000 euros for those of other contracting authorities and 5 404 000 euros for works. All figures are on the thresholds page.
  • An authority may apply a mandatory procedure of the Act also to a contract whose estimated value does not reach the threshold concerned (§ 15(11)). It may not, however, choose a method of calculation or divide the procurement in order to disregard the rules of the Act (§ 23(8), § 28(2)).

The general rules

  • Without VAT. All estimated values in the Act are calculated exclusive of value added tax (§ 23(1)).
  • Everything that will be paid. The estimated value includes the estimated total amount to be paid on performance of the contract, taking into account possible future obligations under the contract and its renewal (§ 23(2) cl 1). It also includes prizes or participation fees paid to participants (§ 23(2) cl 5) and, for a design contest followed by a service contract, the value of that contract (§ 23(2) cl 2); see the full list in § 23(2).
  • Market price before the start. The authority relies on the price level that corresponds to the average market price immediately before the procurement is commenced and that is effective when it is commenced (§ 23(3)).
  • Framework agreements and dynamic purchasing systems. The basis is the maximum total value of all contracts to be awarded under the framework agreement or the system during its period of validity (§ 23(4)). See the guide on framework agreements.
  • Additional contracts announced in advance. Where the contract notice announces that a new service or works contract may later be awarded in a negotiated procedure without prior publication, the value of those additional services or works is included in the estimated value (§ 23(7)).
  • Operational units. Where the authority consists of several units, the estimated total value of the procurements of all units is generally taken into account. Only where a separate unit is independently responsible for its own procurement, or a lot of it, may the value of that unit's procurement alone be relied on (§ 23(6)).
  • No method may be used to avoid the rules. None of the grounds for calculating the value may be used to disregard the rules or requirements of the Act. Where the value can be calculated by several methods and at least one of them gives a value equal to or above the simple procurement threshold or the international threshold, the authority must use that method (§ 23(8)).
  • Register. When commencing a procurement, except a negotiated procedure without prior publication, the authority files the estimated value with the register and states whether it wants it published in the contract notice or concession notice (§ 23(9)).

Supplies and services

  • Lease, rental or hire-purchase of supplies. For a fixed term of up to 12 months, the estimated total value during the term (§ 24(1) cl 1); for a fixed term over 12 months, the total value together with interest and the estimated residual value of the supplies at the end of the term (§ 24(1) cl 2); without a fixed term, or where the term cannot be defined, the estimated monthly value multiplied by 48 (§ 24(1) cl 3).
  • Regular or renewed contracts. For supplies or services that are regular in nature or intended to be renewed within a given period, the authority takes either the total value of the successive contracts of the same type in the preceding 12 months or financial or budgetary year, adjusted where possible for expected changes in quantity or price (§ 24(2) cl 1), or the estimated total value of the successive contracts in the 12 months or financial or budgetary year following the first contract (§ 24(2) cl 2). Where one of the two methods reaches a threshold, § 23(8) requires it.
  • Insurance, banking and design services. The basis is the premium and other remuneration, the fees, commissions, interest and other remuneration, or the fees, commissions and other remuneration for the design service (§ 24(3)).
  • Services without a total value. For a fixed term of up to 48 months, the estimated total value during the term (§ 24(4) cl 1); without a fixed term or for a term over 48 months, the monthly value multiplied by 48 (§ 24(4) cl 2).

Works and concessions

  • Works. The estimated value covers both the cost of the works and the estimated value of the supplies and services that the authority makes available to the tenderer for executing the works, at the time they are made available (§ 25).
  • Concessions. The authority calculates the value by an objective method set out in the procurement documents (§ 26(1)), taking into account in particular options and extensions, revenue from users' fees and fines, payments and financial advantages from the authority, other public bodies and third parties, sales of assets, supplies and services made available to the concessionaire, and prizes and payments to candidates or tenderers (§ 26(2)). Where the value of the concession at award exceeds its estimated value by at least 20 per cent, that value is deemed its estimated value (§ 23(5)).

Lots within one procedure

The authority may divide a procurement into lots within a single procedure (§ 27(1)). It then:

  • Counts all lots together. The estimated value of the procurement is the estimated total value of all lots (§ 27(1)).
  • Says who may bid for what. The contract notice or other procurement documents state whether a tenderer may tender for one, several or all lots (§ 27(1)).
  • May cap the number of lots per tenderer. The authority may state a maximum number of contracts per tenderer (§ 27(3)) and must then set objective and non-discriminatory rules for choosing which lots a tenderer receives where evaluation would give it more (§ 27(4)).
  • May combine contracts. Contracts for several lots won by one tenderer may be combined into a single contract if the procurement documents provide for it and identify the lots or groups of lots that may be combined (§ 27(5)).
  • Gives reasons for not dividing. Where a procurement at or above the international threshold is not divided into lots, the authority states the reasons in the procurement documents. This duty does not apply to contracts awarded under a framework agreement or a dynamic purchasing system (§ 27(2)).

Separate procurements and splitting

  • The aggregate decides the procedure. The authority may buy lots separately, in separate procurements, provided it applies to each lot the rules for a contract whose estimated value equals the sum of the estimated values of all lots (§ 28(1)).
  • Splitting to avoid the Act is prohibited. The authority may not divide a procurement for the purpose of disregarding the rules or requirements of the Act, especially where the supplies, services or works are interoperable or necessary for the same purpose. Division is allowed where objective reasons justify it (§ 28(2)).
  • The 20 per cent exception. Except for concession contracts, the authority may apply to certain lots the rules that correspond to the value of each such lot, provided that those lots together do not exceed 20 per cent of the total estimated value of the whole procurement (§ 28(3)).
  • Limits above the international threshold. Where the total of all lots equals or exceeds the international threshold, the 20 per cent exception may be used only for lots each valued below 80 000 euros for supplies or services (§ 28(4) cl 1) or below one million euros for works (§ 28(4) cl 2).

The procedures themselves are in the guide on the simple procedure and the FAQ on thresholds and procedures; smaller purchases in the FAQ on purchases below the threshold; planning in the guide on procurement rules and the procurement plan. This guide repeats the Act and does not cover case law on when purchases form one procurement.