Practical guide
Contestation: what a contracting authority does when a procurement is contested
Who may contest, within which periods, and what the contracting authority does when a contestation notice reaches it: the response, suspension, the decision of the Review Committee, the standstill period and the voidness of a contract.
Reviewed by Mara Ribeiro Duarte, Head of Public Sector at Closer · 20 November 2026
Legal basis§ 185(1) · § 185(2) · § 185(4) · § 185(5) · § 186 · § 189(1) · § 189(2) cl 2 · § 189(2) cl 3 · § 189(4) · § 189(4¹) · § 189(5) · § 189(6) · § 189(7) · § 189(8) · § 189(9) · § 189(10) · § 120(2) · § 125(9) · § 194(2) · § 201 · § 194(4) · § 194(5) · § 194(9) · § 193(1) · § 193(2) · § 193(9) · § 193(8) · § 193(5) · § 193(6) · § 197(1) cl 3 · § 192(3) cl 5 · § 200(1) · § 197(1) · § 198(1) · § 198(3) · § 200(4) · § 200(6) · § 201(1) · § 201(2) · § 201(3) · § 201(3¹) · § 120(4) · § 121(1) cl 1 · § 121(2) · § 31(1) · § 201(5) · § 8(2) · § 121(4) · § 197(3) · § 197(4) · § 185(6) · official text
Who may contest, and what
A tenderer, candidate or economic operator interested in participating (the contesting party) may contest the actions of the contracting authority by filing a contestation notice with the Review Committee, if an infringement of the Act by the authority infringes its rights or adversely affects its interests (§ 185(1)). A notice may be filed against the procurement documents and against decisions such as exclusion, selection, rejection of a tender or declaring a tender successful (§ 185(2)). Some grounds concern the contract itself (§ 185(4)); several of them do not apply where the awarded contract is worth less than the simple procurement threshold (§ 185(5)). A statutory fee is paid on filing (§ 186).
Time limits
The Act sets these periods for a notice to reach the Review Committee (see the deadlines page). This guide repeats the wording of the Act and does not go into how periods are counted.
- General: ten days from the day the contesting party learned or should have learned of the infringement, but not after the contract is concluded (§ 189(1)).
- Procurement documents: at least five working days before the closing date, where the estimated value is at least the simple procurement threshold (§ 189(2) cl 2); where time limits are shortened, ten days from making the document available electronically, but not after the closing date (§ 189(2) cl 3).
- Simple procedure, and procurements below the simple procurement threshold: five working days (§ 189(4), § 189(4¹)).
- Contract under a framework agreement: seven days (§ 189(5)).
- Optional notice: ten days from its publication in the register (§ 189(6)).
- Against the contract itself: 30 days from publication of the contract award notice (§ 189(7)); six months from conclusion where no notice was filed (§ 189(8)); 30 days from learning of the infringement where the rules on reopening competition under a framework agreement were breached (§ 189(9)).
- Compensation for harm: one year from conclusion of the contract (§ 189(10)).
The authority may not give its acceptance to the contract during the standstill period: 14 days (§ 120(2)), seven working days in the simple procedure (§ 125(9)).
What the authority does when a notice is filed
- Notification. If there is no ground to dismiss the notice, the Review Committee informs the authority and sends it a copy (§ 194(2)). A contract concluded after the authority receives that notification and before the conditions of § 201 are met is void (§ 194(4)).
- Response. The authority files a written response within three working days of receiving the copy, with the documents the Committee requires, and may propose a way to resolve the notice (§ 194(5)). Further explanations are due within two working days of the Committee's request (§ 194(9)).
- Suspension. On the contesting party's reasoned application the Committee may suspend the procurement at any stage, deciding within three working days (§ 193(1), § 193(2)). The authority notifies the known operators through the register without delay (§ 193(9)). If the closing date arrives during the suspension, it extends the time limit by a reasonable time and proposes that tenderers extend the validity of their tenders (§ 193(8)).
- Permission to conclude. Where the proceedings are the only obstacle to the contract and a significant public interest outweighs the harm to the contesting party, the Committee may, on the authority's reasoned application, permit the contract to be concluded; it considers the application within five working days (§ 193(5), § 193(6)).
- Ending it earlier. The authority may recognise the notice as justified (§ 197(1) cl 3). If it declares the procedure ineffective, revokes the contested decision or otherwise removes the infringement, the Committee dismisses the notice (§ 192(3) cl 5).
The decision and what follows
- Decision. The Committee decides the merits within 30 days of receiving a notice free of defects, or within 35 days if the notice was amended or supplemented (§ 200(1)). Proceedings end, among other ways, by settlement, withdrawal, recognition by the authority, a decision denying or granting the notice, or dismissal (§ 197(1)).
- Costs. Where the authority recognises the notice or it is granted in full, the authority pays the contesting party's statutory fee, expert fees and reasonable representative costs (§ 198(1)); where it is denied or withdrawn, the contesting party pays the authority's expert fees and reasonable representative costs (§ 198(3)).
- Effect. The decision enters into effect once the period for going to court has passed without a complaint (§ 200(4)). A decision granting the notice binds the authority (§ 200(6)).
- Resuming and concluding. The authority may not resume a suspended procurement or give its acceptance to the contract before 14 days have passed from the announcement of a decision denying or granting the notice (§ 201(1), § 201(2)). After most other endings the period is seven days (§ 201(3)). After notice of an appeal, no acceptance may be given until the final court decision has entered into effect (§ 201(3¹)).
When a contract is void
The Act makes a contract void in defined cases, for example when it is concluded before the standstill period has expired (§ 120(4)), without a required contract notice (§ 121(1) cl 1, subject to § 121(2)), in breach of the rules on reopening competition under a framework agreement (§ 31(1)), contrary to a decision of the Review Committee (§ 200(6)) or in breach of the restrictions on resuming and concluding (§ 201(5)). A breach of the Act does not otherwise affect the validity of a contract (§ 8(2)), and voidness can be relied on only once established in accordance with the Act (§ 121(4)).
When it grants a notice against the contract itself, the Committee may declare the contract void or leave it in force while shortening its term, having regard to a significant public interest (§ 197(3)). Costs of delay, of a new procurement or of replacing the contractor are not such an interest, except where voidness would have disproportionate consequences (§ 197(4)). An economic operator that lost the contract because of an unlawful decision or procurement document may, after the contract is concluded, apply to the Committee for compensation for harm (§ 185(6)).
See also the FAQ on contestation.
Related pages
Previous guide
Technical specifications, brands and standards
Next guide
Estimated value of a public contract and dividing a procurement into lots