These answers describe exclusion, selection and award in the procedures of Chapter 2 as in force from 1 November 2026 (§ 95, § 98, § 117). In the simple procedure the Act requires a contracting authority in the public sector, outside defence and security, to verify before awarding the contract that the exclusion grounds of § 95(1) do not apply (§ 125(7)), and to apply the provisions on award criteria, abnormally low tenders and the award decision unless the procurement documents provide otherwise (§ 125(5)). Procurements started before 1 November 2026 are completed under the earlier version of the Act (§ 219³).
When must a tenderer or candidate be excluded?
The contracting authority does not award a contract to, and excludes from the procedure, a tenderer or candidate that itself, or whose board member or other person authorised to represent, control or decide for it, has been convicted of the offences listed in § 95(1) cl 1, § 95(1) cl 2 or § 95(1) cl 3; that has tax arrears or overdue social security contributions (§ 95(1) cl 4); or with which awarding the contract would breach an international or Government sanction (§ 95(1) cl 5). Convictions count for as long as they remain in the criminal records database or are unspent, but for not more than five years from the judgment taking effect (§ 95(2)). The authority need not apply the first four grounds if awarding the contract is indispensable for overriding reasons in the general interest and no contract would be awarded otherwise; it then makes a reasoned written decision (§ 95(3)). Before excluding for a tax debt it gives the tenderer or candidate, once during the procedure, at least three working days to pay or defer the debt (§ 95(6)).
Legal basis§ 95(1) cl 1 · § 95(1) cl 2 · § 95(1) cl 3 · § 95(1) cl 4 · § 95(1) cl 5 · § 95(2) · § 95(3) · § 95(6) · official text
How are exclusion grounds verified, and what is the Single Procurement Document?
In verifying exclusion grounds the authority applies the rules on the Single Procurement Document (§ 96(1)). It requires each tenderer or candidate to submit one, on the European Commission’s standard form, as preliminary evidence that no exclusion ground applies and that the selection criteria are met (§ 104(1), § 104(3)). Before awarding the contract it requires the successful tenderer, or the tenderer it intends to declare successful, to submit the documents behind the declarations, and verifies them (§ 104(8)). To verify that no exclusion ground applies it may require only a criminal records extract or equivalent document and a certificate of the competent authority on tax arrears and insolvency (§ 96(2)); the sanctions ground is verified on the tenderer’s declaration (§ 96(2¹)). In the open procedure the authority may check and evaluate tenders before verifying exclusion and selection, if it ensures that the contract is not awarded to a tenderer that should have been excluded or does not meet the selection criteria (§ 52(3)).
Legal basis§ 96(1) · § 104(1) · § 104(3) · § 104(8) · § 96(2) · § 96(2¹) · § 52(3) · official text
Can a tenderer remedy an exclusion ground (self-cleaning)?
In a procurement whose estimated value equals or exceeds the international threshold, a tenderer or candidate to which one of the exclusion grounds named in § 97(1) applies may submit evidence that it has taken measures to restore its reliability, for example compensating the harm caused, cooperating actively with investigators and taking technical, organisational or personnel measures. The authority assesses the evidence; if it finds it sufficient, it decides by a reasoned written decision not to exclude the tenderer or candidate and may award it the contract (§ 97(2)). Below the international threshold the authority may apply this possibility if it provides for it in the procurement documents (§ 97(3)). The tax-arrears ground has its own mechanism, the opportunity to pay or defer the debt (§ 95(6)).
Legal basis§ 97(1) · § 97(2) · § 97(3) · § 95(6) · official text
What selection (qualification) conditions may be set?
The contracting authority may verify a tenderer’s or candidate’s suitability to pursue the professional activity and set selection criteria for its economic and financial standing and its technical and professional ability; they must correspond to the nature, quantity and purpose of the contract and be proportionate (§ 98(1)). The required annual net turnover may not exceed twice the estimated value of the contract unless the procurement documents justify more by the risks of performance (§ 100(3)). As evidence of experience the authority may ask for lists of works contracts performed within the 60 months and of supply or service contracts performed within the 36 months before the procurement started (§ 101(1) cl 1, § 101(1) cl 2), and may take earlier contracts into account to ensure sufficient competition (§ 101(2)). A tenderer may not be left unselected only because it has no earlier public contracts (§ 98(3)), and may rely on the resources of other economic operators (§ 103(1)). Where it has set selection criteria, the authority decides on selection by a reasoned written decision (§ 98(5)).
Legal basis§ 98(1) · § 100(3) · § 101(1) cl 1 · § 101(1) cl 2 · § 101(2) · § 98(3) · § 103(1) · § 98(5) · official text
How are award criteria set and the successful tender chosen?
The contracting authority sets in the procurement documents award criteria that are related to the subject matter of the contract and ensure real competition; selection criteria may not be used as award criteria, except data on the education and professional qualifications of the persons responsible for performance where they are not used for selection (§ 85(1)). It identifies the most economically advantageous tender, taking into account in particular the best price-quality ratio and the price or cost, including life-cycle costs (§ 85(3), § 86). Price or cost alone may be used only where the tender’s advantage depends solely on it and all other terms of the future contract are exhaustively determined (§ 85(4)). The documents state the relative weighting of each criterion (§ 85(9)). The authority assesses the suitable tenders against the criteria and declares the most economically advantageous tender successful by a reasoned written decision (§ 117(1)). If a tender contains a calculation error, the authority corrects it and notifies the tenderer, who has two working days to say whether it agrees; if not, the tender is rejected (§ 117(3)).
Legal basis§ 85(1) · § 85(3) · § 86 · § 85(4) · § 85(9) · § 117(1) · § 117(3) · official text