Time limits for tenders
Minimum time limits for tenders and requests to participate in the open, restricted and simple procedures, when they can be shortened or extended, tender validity and the standstill period.
Reviewed by Mara Ribeiro Duarte, Head of Public Sector at Closer · 20 November 2026
These answers cover the minimum time limits for tenders in the open procedure (§ 93), the restricted procedure (§ 94), the simple procedure (§ 125(4)) and the specific procedure for social and other specific services (§ 126(6¹)), as in force from 1 November 2026. Procurements started before that date are completed under the earlier version of the Act, some of whose time limits were different (§ 219³). They also cover shortening and extension, clarifications, the day and hour of the closing date, tender validity and the standstill period. Time limits are given as the Act words them (this page does not explain how days are counted), and the figures are also in the deadlines table.
What is the minimum time limit for tenders in the open procedure?
In the open procedure the time limit for tenders may not be shorter than 30 days (supplies and services) from the submission of the contract notice to the Publications Office where all communication in the procedure is electronic (§ 93(1) cl 4) and 35 days where it is not (§ 93(1) cl 5); for works contracts the minimum is 45 days from the same moment (§ 93(1) cl 6). The contracting authority sets the time limit with regard to the subject matter of the contract, in particular its complexity and quantity (§ 92(1)). If the register sends a notice to remedy defects in the contract notice, the authority sets a new time limit counted from the filing of the notice free of defects (§ 93(3)).
Legal basis§ 93(1) cl 4 · § 93(1) cl 5 · § 93(1) cl 6 · § 92(1) · § 93(3) · official text
What are the minimum time limits in the restricted procedure?
The time limit for requests to participate may not be shorter than 30 days from the submission of the contract notice to the Publications Office (§ 94(1) cl 2). The time limit for tenders after the invitation to submit a tender may not be shorter than 25 days from the invitation where all communication is electronic (§ 94(3) cl 3) and 30 days where it is not (§ 94(3) cl 4). The same minimums apply in the competitive procedure with negotiation, the competitive dialogue and the innovation partnership (§ 94(1), § 94(3)). If the register sends a notice to remedy defects in the contract notice, the authority sets a new time limit for requests counted from the filing of the notice free of defects (§ 94(2)).
Legal basis§ 94(1) cl 2 · § 94(3) cl 3 · § 94(3) cl 4 · § 94(1) · § 94(3) · § 94(2) · official text
When can the time limits be shortened?
In the open procedure the 30- and 35-day time limits may be shortened to 15 days, and the 45-day time limit for works to 25 days, where the authority has filed an indicative notice that contained all the mandatory contract-notice information then available, or where urgent circumstances, whose reasons are set out in the procurement documents, prevent it from keeping the minimum time limits (§ 93(2)). In the restricted procedure and the competitive procedure with negotiation the time limit for tenders may be shortened on the same grounds to ten days (supplies and services) or 15 days (works) (§ 94(4)), and the time limit for requests to participate to 15 days on the ground of urgency (§ 94(5)). The indicative notice must be filed 35 days to 12 months before the contract notice (§ 75(3)). § 125(4) states the minimum for the simple procedure without an exception.
Legal basis§ 93(2) · § 94(4) · § 94(5) · § 75(3) · § 125(4) · official text
How do clarifications and changes to the documents affect the time limit?
The contracting authority makes clarifications electronically available within three working days of receiving a request (§ 46(1)). It need not answer a request if less than six days remain between its receipt and the closing date for tenders (four days in the cases of § 93(2) cl 2 and § 94(4); two working days in the simple procedure and the specific procedure for social and other specific services) (§ 46(2)). If the authority modifies the procurement documents, it must extend the time limit so that, counted from the filing of the modified contract notice with the register or – if the notice is not modified – from making the modified documents available, it equals at least half of the respective minimum time limit; there are exceptions, for example where only contact details change (§ 82(1), § 82(2)); in the simple procedure the minimum of § 125(4) is taken into account (§ 125(5)). The authority may also extend the time limit on its own initiative; shortening is not allowed (§ 82(4)).
Legal basis§ 46(1) · § 93(2) cl 2 · § 94(4) · § 46(2) · § 82(1) · § 82(2) · § 125(4) · § 125(5) · § 82(4) · official text
On which day and at what time may the closing date be set?
The contracting authority may set the closing date for tenders or requests to participate on a day from Monday to Friday, other than a public holiday, between 9:00 and 16:00 (§ 92(2)). These rules are in Chapter 2: § 125(5) does not name § 92 among the provisions the authority follows in the simple procedure, but § 125(2) lets the authority rely on other provisions of the Act when setting the rules in the procurement documents. Where tenders can be submitted only electronically and the electronic system has not been operational for more than 15 minutes at a time within eight hours before the closing date, the procedure is suspended automatically and the closing date does not arrive; once the system works again the authority extends the time limit by a reasonable time, to at least one day from the notice (§ 81(2), § 81(3)).
Legal basis§ 92(2) · § 125(5) · § 92 · § 125(2) · § 81(2) · § 81(3) · official text
How long is a tender binding, and what is the standstill period?
A tender binds the tenderer from the closing date at least until the minimum period of validity stated in the procurement documents (§ 110(1)); unless the documents provide otherwise it is binding for three months from the closing date (§ 110(1¹)). If the procedure has not ended, the authority must propose an extension of the validity to each participating tenderer at least ten days before it expires, and the tenderer answers within five working days (§ 112(2)). The authority may not give its acceptance to conclude the contract before 14 days have passed from the submission of the notice on the decision that is to be followed by the contract (§ 120(2)); in the simple procedure the standstill period is seven working days (§ 125(9); five working days for procurements started before 1 November 2026, § 219³). It need not be applied to contracts awarded under a framework agreement or a dynamic purchasing system, in a negotiated procedure without prior publication or where only one tenderer participates when the decision is made (§ 120(3)). A contract awarded before the standstill period has expired is void (§ 120(4)).
Legal basis§ 110(1) · § 110(1¹) · § 112(2) · § 120(2) · § 125(9) · § 219³ · § 120(3) · § 120(4) · official text