Public Procurement Act · Chapter 1
§ 23. Rules on calculation of estimated value of public procurement
Chapter 1 · General Provisions · Division 5: Calculation of Estimated Value of Public Procurement and Subdivision of Public Procurement into Lots
Changed 1 November 2026
† Our own working translation of words that the reform of 1 November 2026 changed: Riigi Teataja has not yet published an official English text of them, and replaces ours when it does.
(1) All of the estimated values, estimated total values, values and total values mentioned in this Act, and the fees and payments serving as the basis for the aforementioned are calculated exclusive of value added tax.
(2) The estimated value of public procurement includes the following:
1) the estimated total amount to be paid on performance of the public contract, taking into account, among other things, possible future obligations arising from the contract as well as renewal of the contract;
2) possible prizes awarded in a design contest or participation fees and the estimated value of a public service contract where the contracting authority or entity intends to award a public service contract as a result of the design contest;
3) total turnover of the works performed and services provided under a concession contract along with the value of the supplies required for the works and services;
4) the maximum estimated value of research and development taking place at all stages of the planned innovation partnership and the maximum estimated value of the supplies, services or works developed and delivered as a result of the partnership;
5) the participation fee covering the participation expenses or the prize, provided that the contracting authority or entity pays or awards it to the participants in the public procurement.
(3) The price level that must be relied on when calculating the estimated value of a public procurement is the level that corresponds to the average market price at the time immediately preceding commencement of the procurement and that must be effective at the time of commencement.
(4) The basis for calculating the estimated value of a framework agreement or public contracts awarded under a dynamic purchasing system is the maximum total value of public contracts awarded under the framework agreement or dynamic purchasing system during the period of validity of the framework agreement or dynamic purchasing system.
(5) Where the value of a concession contract at the time of awarding the concession contract exceeds the estimated value of the concession contract by at least 20 per cent, the value of the concession contract is deemed the estimated value of the concession contract.
(6) Where the contracting authority or entity consists of multiple operational units, the estimated total value of the public procurement of all of the units is generally taken into account when determining the estimated value of the authority’s or entity’s procurement. Where a separate operational unit is independently responsible for its public procurement or for a lot of such a procurement, the estimated value of the procurement of the unit may be relied on when calculating the estimated value of the procurement.
(7) Where in a procurement procedure with a call for competition the possibility of awarding a new public service or works contract is communicated in a contract notice in accordance with the negotiated procedure without prior publication of a contract notice on the grounds provided by subsection 5 of § 49 of this Act, the estimated total value of the services or works bought under such an additional public contract is included in the estimated value of the public contract.
(8) None of the chosen grounds for calculation of the estimated value of public procurement may be used for disregarding the rules or requirements established for carrying out public procurement. Where, based on the provisions of this Chapter, it is possible to calculate the estimated value of public procurement using various methods and, when using at least one of these methods, the estimated value of the public procurement would equal or exceed the simple procurement threshold or international threshold, the contracting authority or entity must calculate the estimated value of the public procurement based on that method.†
Wording until 31 October 2026
None of the chosen grounds for calculation of the estimated value of public procurement may be used for disregarding the rules or requirements established for carrying out public procurement. Where, based on the provisions of this Chapter, it is possible to calculate the estimated value of public procurement using various methods and, when using at least one of these methods, the estimated value of the public procurement would equal or exceed the simple procurement threshold, public procurement threshold or international threshold, the contracting authority or entity must calculate the estimated value of the public procurement based on that method.
(9) When commencing public procurement, except by negotiated procedure without prior publication of a contract notice, the contracting authority or entity files with the register the particulars of the estimated value of the procurement and states whether the authority or entity requests that the estimated value be published in the contract notice or concession notice.
The section as it read until 31 October 2026
(1) All of the estimated values, estimated total values, values and total values mentioned in this Act, and the fees and payments serving as the basis for the aforementioned are calculated exclusive of value added tax.
(2) The estimated value of public procurement includes the following:
1) the estimated total amount to be paid on performance of the public contract, taking into account, among other things, possible future obligations arising from the contract as well as renewal of the contract;
2) possible prizes awarded in a design contest or participation fees and the estimated value of a public service contract where the contracting authority or entity intends to award a public service contract as a result of the design contest;
3) total turnover of the works performed and services provided under a concession contract along with the value of the supplies required for the works and services;
4) the maximum estimated value of research and development taking place at all stages of the planned innovation partnership and the maximum estimated value of the supplies, services or works developed and delivered as a result of the partnership;
5) the participation fee covering the participation expenses or the prize, provided that the contracting authority or entity pays or awards it to the participants in the public procurement.
(3) The price level that must be relied on when calculating the estimated value of a public procurement is the level that corresponds to the average market price at the time immediately preceding commencement of the procurement and that must be effective at the time of commencement.
(4) The basis for calculating the estimated value of a framework agreement or public contracts awarded under a dynamic purchasing system is the maximum total value of public contracts awarded under the framework agreement or dynamic purchasing system during the period of validity of the framework agreement or dynamic purchasing system.
(5) Where the value of a concession contract at the time of awarding the concession contract exceeds the estimated value of the concession contract by at least 20 per cent, the value of the concession contract is deemed the estimated value of the concession contract.
(6) Where the contracting authority or entity consists of multiple operational units, the estimated total value of the public procurement of all of the units is generally taken into account when determining the estimated value of the authority’s or entity’s procurement. Where a separate operational unit is independently responsible for its public procurement or for a lot of such a procurement, the estimated value of the procurement of the unit may be relied on when calculating the estimated value of the procurement.
(7) Where in a procurement procedure with a call for competition the possibility of awarding a new public service or works contract is communicated in a contract notice in accordance with the negotiated procedure without prior publication of a contract notice on the grounds provided by subsection 5 of § 49 of this Act, the estimated total value of the services or works bought under such an additional public contract is included in the estimated value of the public contract.
(8) None of the chosen grounds for calculation of the estimated value of public procurement may be used for disregarding the rules or requirements established for carrying out public procurement. Where, based on the provisions of this Chapter, it is possible to calculate the estimated value of public procurement using various methods and, when using at least one of these methods, the estimated value of the public procurement would equal or exceed the simple procurement threshold, public procurement threshold or international threshold, the contracting authority or entity must calculate the estimated value of the public procurement based on that method.
(9) When commencing public procurement, except by negotiated procedure without prior publication of a contract notice, the contracting authority or entity files with the register the particulars of the estimated value of the procurement and states whether the authority or entity requests that the estimated value be published in the contract notice or concession notice.
Amended by RT I, 01.07.2017, 1 (in force from 18 October 2018) · RT I, 03.07.2026, 3 (in force from 1 November 2026)
On this site
Previous section
§ 22 — Rules for carrying out public procurement of works and of design of buildings
Next section
§ 24 — Calculation of estimated value of public supply or service contract