Modifying a public contract

When a public contract may be modified without a new procurement, how framework agreements and subcontracting work, and when the contract may or must be terminated under the Estonian Public Procurement Act.

Updated 19 November 20267 questions

Reviewed by Mara Ribeiro Duarte, Head of Public Sector at Closer · 20 November 2026

These answers cover the modification of a public contract after it has been awarded (§ 123), framework agreements and the contracts awarded under them (§ 29, § 30, § 31), subcontracting (§ 122) and termination (§ 124), as in force from 1 November 2026. The provisions on modification and termination sit in Chapter 2; the simple procedure and the specific procedure for social and other specific services refer to them (§ 125(8), § 126(10)). Where the earlier version of the Act differs, the answers say so; the last answer deals with the transition to the version of 2026 (§ 219³).

When may a public contract be modified without a new procurement?

A public contract is awarded on the terms set out in the procurement documents and in accordance with the successful tender (§ 120(1)). It may be modified without a new procurement only in the cases of § 123(1): (1) the overall nature of the contract is unchanged and the modifications together exceed neither the international threshold of § 14(3) (or, in defence and security, that of § 14(4)) nor ten per cent of the initial value (15 per cent for works; ten per cent for concessions) (§ 123(1) cl 1); (2) the modification was provided for in clear, precise and unequivocal clauses of the procurement documents (§ 123(1) cl 2); (3) additional supplies, services or works from the same operator, where a change of operator would cause significant inconvenience or extra cost and be unreasonable for economic or technical reasons, with no modification raising the value by more than 50 per cent (§ 123(1) cl 3); (4) circumstances unforeseeable to a diligent authority, the overall nature unchanged and no modification raising the value by more than 50 per cent (§ 123(1) cl 4); (5) the operator is replaced under a clause in the procurement documents (§ 123(1) cl 5); (6) the operator is replaced on its restructuring by one not subject to exclusion that meets the selection criteria, without other substantial changes (§ 123(1) cl 6); (7) the modification is not substantial, whatever its value (§ 123(1) cl 7).

Legal basis§ 120(1) · § 123(1) · § 14(3) · § 14(4) · § 123(1) cl 1 · § 123(1) cl 2 · § 123(1) cl 3 · § 123(1) cl 4 · § 123(1) cl 5 · § 123(1) cl 6 · § 123(1) cl 7 · official text

What makes a modification substantial?

A modification is substantial where it alters the overall nature of the contract considerably, in particular where it introduces a condition that, had it been in the procurement documents, would have attracted more participants or increased the number of tenders to be declared suitable (§ 123(2) cl 1); shifts the balance of the contractual obligations in favour of the economic operator in a way the contract does not provide for (§ 123(2) cl 2); extends the scope of the subject matter of the contract considerably (§ 123(2) cl 3); or replaces the operator in a case other than those of § 123(1) cl 5 and § 123(1) cl 6 (§ 123(2) cl 4). Where the contract contains an indexation clause, the values in § 123(1) cl 1, § 123(1) cl 3 and § 123(1) cl 4 are calculated from the indexed value; where a concession contract has no indexation clause, the indexed value is calculated from the average inflation in Estonia published by Statistics Estonia (§ 123(4)).

Legal basis§ 123(2) cl 1 · § 123(2) cl 2 · § 123(2) cl 3 · § 123(1) cl 5 · § 123(1) cl 6 · § 123(2) cl 4 · § 123(1) cl 1 · § 123(1) cl 3 · § 123(1) cl 4 · § 123(4) · official text

Do the value limits apply everywhere, and must a modification be reported?

The value limit in § 123(1) cl 3 and § 123(1) cl 4 does not apply to procurements in the network sector or to concession contracts in the fields of activity named in Annex II to Directive 2014/23/EU (§ 123(3)). A modification made under § 123(1) cl 3 or § 123(1) cl 4 is notified to the register by a contract modification notice within 30 days of the modification, except where the modified contract was awarded under a framework agreement (§ 123(5)); the earlier version of the Act gave ten days. Within 30 days after the contract is completed, the authority files the actual value of the contract and the modifications for which no modification notice was filed (§ 83(7)).

Legal basis§ 123(1) cl 3 · § 123(1) cl 4 · § 123(3) · § 123(5) · § 83(7) · official text

What rules apply to framework agreements and the contracts awarded under them?

Framework agreements are governed by the provisions on public contracts unless the Act provides otherwise (§ 29(1)). The term is up to four years unless a longer term is justified; an agreement without a fixed term is prohibited (§ 29(2)). Contracts under it are awarded only by authorities identifiable from the procurement documents and only to the tenderers party to the agreement, without substantially amending its terms (§ 30(1), § 30(2)). If an agreement with several tenderers does not lay down all the terms, the authority reopens the competition among them (§ 30(4)); if it does, the authority may award without reopening or partly on the agreement and partly on a reopening (§ 30(6)), and the agreement may allow awards to a freely chosen party up to 20 per cent of the value of the framework agreement, each contract being below the simple procurement threshold (§ 30(8)). A contract awarded in breach of the conditions for reopening competition is void, unless the authority applied the seven-day notice procedure of § 30(11) (§ 31(1)).

Legal basis§ 29(1) · § 29(2) · § 30(1) · § 30(2) · § 30(4) · § 30(6) · § 30(8) · § 30(11) · § 31(1) · official text

What does the Act say about subcontracting?

In the procurement documents the contracting authority may require tenderers to state the share and nature of the contract they intend to subcontract and the names of the planned subcontractors (§ 122(1)). For works contracts and works concessions of at least 500 000 euros, and for on-site service contracts under the authority’s direct supervision at or above the international threshold, it must require the contractor to give the names, contact details and legal representatives of the subcontractors known at the start of performance and, for works, of those who join later (§ 122(2)). For works of at least 500 000 euros it verifies the exclusion grounds of § 95(1) for the subcontractors named in the successful tender and for those added later with at least ten per cent of the contract value (§ 122(5)), and requires a subcontractor to be replaced where such a ground applies (§ 122(7)). A subcontractor of such a works contract may ask the authority whether the contractor has been paid for the subcontractor’s proven work (§ 122(8)), and the authority may withhold the corresponding part of the contractor’s claim on the subcontractor’s reasoned application (§ 122(9)). The authority may apply the section more widely if the procurement documents so provide (§ 122(11)).

Legal basis§ 122(1) · § 122(2) · § 95(1) · § 122(5) · § 122(7) · § 122(8) · § 122(9) · § 122(11) · official text

When may or must the authority terminate the contract or withdraw from it?

The contracting authority has the right to terminate or withdraw from a contract where modifications not permitted under § 123 have been made (§ 124(1) cl 1); where one of the first four exclusion grounds of § 95(1) applied to the contractor at the time of award and it should have been excluded (§ 124(1) cl 2), or applies during performance (§ 124(1) cl 2¹); or where the Court of Justice has found in infringement proceedings that EU obligations were breached in the procurement or the award (§ 124(1) cl 3). It must terminate or withdraw where the sanctions ground of § 95(1) cl 5 applied to the contractor at the time of award or at any time after it, or where continued performance would breach an international or Government sanction (§ 124(1¹) cl 1, § 124(1¹) cl 2), and it then notifies the Financial Intelligence Unit within three working days (§ 124(1²), § 179¹(1)). If a contractor that has received the acceptance does not start performance within the time set, the authority may terminate early or withdraw and apply § 119 (§ 124(2)).

Legal basis§ 123 · § 124(1) cl 1 · § 95(1) · § 124(1) cl 2 · § 124(1) cl 2¹ · § 124(1) cl 3 · § 95(1) cl 5 · § 124(1¹) cl 1 · § 124(1¹) cl 2 · § 124(1²) · § 179¹(1) · § 119 · § 124(2) · official text

Which version of the rules applies to a contract from a procurement started before 1 November 2026?

§ 219³ provides that procurement proceedings started before 1 November 2026 are completed under the requirements of the version of the Act in force until 31 October 2026. It speaks of completing procedures; its text does not say which version of § 123 or § 124 governs the modification or termination of a contract awarded in such a procedure. For contracts awarded under the Public Procurement Act previously in force, the Act states that § 123 applies to their modification (§ 219(3)) and § 124 to their termination (§ 219(7)). Two points differ from the earlier version of § 123: the notice of a modification under § 123(1) cl 3 or § 123(1) cl 4 is due within 30 days, not ten (§ 123(5)); and the additional purchases of § 123(1) cl 3 now require that a change of operator would be unreasonable for economic or technical reasons, where the earlier text required that it would not be possible.

Legal basis§ 219³ · § 123 · § 124 · § 219(3) · § 219(7) · § 123(1) cl 3 · § 123(1) cl 4 · § 123(5) · official text

Want your procurement documents checked before publication? We will show you how Procurelex Verifika does it.

Request a demo

General information on the Public Procurement Act in force. Not legal advice.