Time limits
Time limits in Estonian public procurement
The time limits of the Public Procurement Act for clarifications, tenders, the standstill period, notices and review, each with the provision it is read from, and a calculator that counts one of them from a date.
Reviewed by Mara Ribeiro Duarte, Head of Public Sector at Closer · 20 November 2026
Count a time limit
Choose a time limit and the date of the fact it runs from. The count shows the first day, the last day counted and where the period ends.
An aid, not legal advice. Check the date against the provision and the facts of your procedure.
How the days are counted here
- The day of the fact (the notice, the publication, the dispatch) does not count: the period starts on the next day.
- Saturdays, Sundays and public holidays count, unless the provision speaks of working days; a period in working days counts only working days.
- A period in months or years ends on the same date of the last month, or on the last day of a month that has no such date.
- A period that ends on a Saturday, a Sunday or a public holiday ends on the next working day.
- A period in days or longer expires at 24.00 on its last day; where the recipient acts in business or a profession, a declaration must reach them by the end of normal working hours on that day.
The time limits shown are those of the version of the Act in force from 1 November 2026. Proceedings commenced before that day are completed under the earlier version (§ 219³).
The Act does not say how its periods are counted: this page applies §§ 135–137 of the General Part of the Civil Code Act (TsÜS) to all of them, the standstill period and the time limits for a contestation notice included. Source in Riigi Teataja: Tsiviilseadustiku üldosa seadus (TsÜS)
Which rules apply to a purchase of a given value? Try the procedure selector
Clarifications
| Time limit | Applies to | What | Counted from | Legal basis |
|---|---|---|---|---|
| 3 working daysmaximum | Every procedure | Making the clarifications available | the receipt of the request for clarification | § 46(1) |
| 6 calendar daysminimum | Standard procedures | A request for clarification the authority must answer: at least this long before the deadline | counted back fromthe deadline for submitting tenders | § 46(2) |
| 4 calendar daysminimum | Standard procedures | The same where the time limits are shortened (§ 93(2) clause 2, § 94(4)) | counted back fromthe deadline for submitting tenders | § 46(2) |
| 2 working daysminimum | Simple procedure | The same in the simple procedure and in the special procedure for social and specific services | counted back fromthe deadline for submitting tenders | § 46(2) |
Tenders and requests to participate
| Time limit | Applies to | What | Counted from | Legal basis |
|---|---|---|---|---|
| 30 calendar daysminimum | Standard procedures | Time limit for tenders in the open procedure (supplies and services, electronic communication) | the submission of the contract notice to the Publications Office | § 93(1) cl 4 |
| 35 calendar daysminimum | Standard procedures | Time limit for tenders in the open procedure (supplies and services, communication not electronic) | the submission of the contract notice to the Publications Office | § 93(1) cl 5 |
| 45 calendar daysminimum | Standard procedures | Time limit for tenders in the open procedure (works) | the submission of the contract notice to the Publications Office | § 93(1) cl 6 |
| 15 calendar daysreduced minimum | Standard procedures | Shortening the time limit of the open procedure after a prior information notice or for urgency (supplies and services) | the submission of the contract notice to the Publications Office | § 93(2) |
| 25 calendar daysreduced minimum | Standard procedures | Shortening the time limit of the open procedure after a prior information notice or for urgency (works) | the submission of the contract notice to the Publications Office | § 93(2) |
| 30 calendar daysminimum | Standard procedures | Time limit for requests to participate (restricted procedure and the others) | the submission of the contract notice to the Publications Office | § 94(1) cl 2 |
| 15 calendar daysreduced minimum | Standard procedures | Shortening the time limit for requests to participate for urgency | the submission of the contract notice to the Publications Office | § 94(5) |
| 25 calendar daysminimum | Standard procedures | Time limit for tenders after the invitation (electronic communication) | the invitation to submit a tender | § 94(3) cl 3 |
| 30 calendar daysminimum | Standard procedures | Time limit for tenders after the invitation (communication not electronic) | the invitation to submit a tender | § 94(3) cl 4 |
| 10 calendar daysreduced minimum | Standard procedures | Shortening the time limit for tenders (supplies and services) | the invitation to submit a tender | § 94(4) |
| 15 calendar daysreduced minimum | Standard procedures | Shortening the time limit for tenders (works) | the invitation to submit a tender | § 94(4) |
| 15 calendar daysminimum | Simple procedure | Time limit for tenders in the simple procedure (supplies and services) | the submission of the contract notice to the register | § 125(4) |
| 25 calendar daysminimum | Simple procedure | Time limit for tenders in the simple procedure (works) | the submission of the contract notice to the register | § 125(4) |
| 10 calendar daysminimum | Social and specific services | Time limit for tenders in the special procedure for social and specific services | the submission of the contract notice to the register or to the Publications Office | § 126(6¹) |
| 3 monthsminimum | Every procedure | Binding force of a tender, unless the procurement documents say otherwise | the deadline for submitting tenders | § 110(1¹) |
Standstill period
Notices
| Time limit | Applies to | What | Counted from | Legal basis |
|---|---|---|---|---|
| 30 calendar daysmaximum | Every procedure | Submitting the contract award notice to the register | the end of the procurement procedure | § 83(1) |
| 12 monthsmaximum | Standard procedures | A prior information notice that allows shorter time limits: no earlier than | counted back fromthe date the contract notice is submitted | § 75(3) |
| 35 calendar daysminimum | Standard procedures | A prior information notice that allows shorter time limits: at least this long before the contract notice | counted back fromthe date the contract notice is submitted | § 75(3) |
Review
| Time limit | Applies to | What | Counted from | Legal basis |
|---|---|---|---|---|
| 10 calendar daysmaximum | Standard procedures | Filing a contestation notice with the Review Committee | the day the contesting party learned of the infringement of its rights | § 189(1) |
| 5 working daysminimum | Standard procedures | Contestation notice against a procurement document: at least this long before the deadline | counted back fromthe deadline for requests, tenders or design proposals | § 189(2) cl 2 |
| 10 calendar daysmaximum | Standard procedures | Contestation notice against a procurement document where the time limits are shortened | making the procurement document available electronically | § 189(2) cl 3 |
| 5 working daysmaximum | Simple procedure | Contestation notice in the simple procedure | the day the contesting party learned of the infringement of its rights | § 189(4) |
| 7 calendar daysmaximum | Standard procedures | Contestation notice in a procedure for a contract under a framework agreement | the day the contesting party learned of the infringement of its rights | § 189(5) |
| 10 calendar daysmaximum | Standard procedures | Contestation notice after the voluntary notice is published | the publication of the voluntary notice in the register | § 189(6) |
| 30 calendar daysmaximum | Standard procedures | Contestation notice to have the contract declared void (contract award notice published) | the publication of the contract award notice in the register | § 189(7) |
| 6 monthsmaximum | Standard procedures | Contestation notice to have the contract declared void (no notice published) | the conclusion of the contract | § 189(8) |
| 30 calendar daysmaximum | Standard procedures | Contestation notice on the ground of clause 6 of subsection 4 of § 185 | the day the contesting party learned of the infringement of its rights | § 189(9) |
| 1 yearmaximum | Standard procedures | Application for compensation for harm to the Review Committee | the conclusion of the contract | § 189(10) |
Public holidays
The national and public holidays of the Holidays Act, which the count treats as non-working days. Saturdays and Sundays are rest days too. Source in Riigi Teataja: Pühade ja tähtpäevade seadus (PTS)
2026
- 1 January 2026New Year's Day
- 24 February 2026Independence Day, anniversary of the Republic of Estonia
- 3 April 2026Good Friday
- 5 April 2026Easter Sunday
- 1 May 2026Spring Day
- 24 May 2026Whit Sunday (Pentecost)
- 23 June 2026Victory Day
- 24 June 2026Midsummer Day
- 20 August 2026Day of Restoration of Independence
- 24 December 2026Christmas Eve
- 25 December 2026Christmas Day
- 26 December 2026Boxing Day (second day of Christmas)
2027
- 1 January 2027New Year's Day
- 24 February 2027Independence Day, anniversary of the Republic of Estonia
- 26 March 2027Good Friday
- 28 March 2027Easter Sunday
- 1 May 2027Spring Day
- 16 May 2027Whit Sunday (Pentecost)
- 23 June 2027Victory Day
- 24 June 2027Midsummer Day
- 20 August 2027Day of Restoration of Independence
- 24 December 2027Christmas Eve
- 25 December 2027Christmas Day
- 26 December 2027Boxing Day (second day of Christmas)
Want your procurement documents checked before publication? We will show you how Procurelex Verifika does it.
Request a demoGeneral information on the Public Procurement Act in force. Not legal advice.