Text of the consolidated version in force from 1 November 2026 (RT I, 03.07.2026, 7). Where this page and Riigi Teataja differ, Riigi Teataja prevails: official textOfficial English translation (it renders the version of 1 October 2026)The Estonian text is the only one with legal force; the English is a translation.

(1) Contestation proceedings are concluded when:

1) the dispute is settled by mutual agreement;

2) the contesting party withdraws their contestation notice;

3) the contracting authority or entity recognises that the contestation notice is justified;

4) the Review Committee decides to deny the contestation notice or the application for compensation for harm;

5) the Review Committee decides to grant the contestation notice in part or in full, setting aside the contracting authority’s or entity’s unlawful public procurement decision or mandating that the authority or entity bring a procurement document into conformity with the requirements prescribed by legislation;

6) the Review Committee makes a decision to grant the application for compensation for harm in part or in full and orders the contracting authority or entity to pay the contesting party compensation for the harm caused by the authority’s or entity’s unlawful decision, operation or procurement document;

7) the Review Committee decides to terminate contestation proceedings following the issuing by the Ministry of Finance of the compliance notice mentioned in § 208 of this Act;

8) the Review Committee decides to dismiss the contestation notice in part or in full where the grounds provided by subsection 3 of § 192 of this Act come to light.

(2) When granting a contestation notice filed under clause 1 of subsection 4 of § 185 of this Act or one concerning the lawfulness of the use of the derogation provided for by §§ 11, 12, 132–134, 153 or 170, the Review Committee, by its decision, bars the award of the public contract.

(3) When granting a contestation notice that has been filed under clauses 2–6 of subsection 4 of § 185 of this Act, the Review Committee may, by its decision:

1) declare the public contract void by virtue of § 31 or 121 of this Act, or

2) leave the public contract in effect but reduce its term of validity – where it has established the presence of circumstances that would make the contract void by virtue of § 31 or 121 of this Act. When making the decision, consideration is given to significant public interests that may be harmed if the contract were void.

(4) For the purposes of this section, economic interests directly related to the public contract in question do not constitute reasons related to significant public interests. Economic interests directly related to the contract include, among other things, costs arising from the postponement of performance of the contract, commencement of new public procurement and replacement of the tenderer performing the contract as well as the costs of legal obligations arising from the voidness of the contract. Economic interests may be deemed a reason related to significant public interests only where – in exceptional circumstances – the declaration of voidness would entail disproportionate consequences.

(5) The conclusion of contestation proceedings in accordance with clause 1, 2 or 3 of subsection 1 of this section is issued as a decision of the Review Committee. Where the dispute is settled by mutual agreement, the contestation notice is withdrawn or is recognised as justified at the hearing, the conclusion of contestation proceedings is stated in the written record of proceedings.

(6) Where the contesting party withdraws the contestation notice before it is considered at a public hearing or before a decision is taken in written procedure, the Review Committee terminates the proceedings by its decision and immediately notifies this to the contracting authority or entity.

(7) The conclusion of contestation proceedings by virtue of clauses 4, 5 or 6 of subsection 1 of this section is issued as a reasoned decision of the Review Committee.

(8) Where contestation proceedings are concluded by virtue of clauses 1, 2, 3 of 7 of subsection 1 of this section, the Review Committee does not assess the lawfulness of the procurement document or decision of the contracting authority or entity.

(9) Where contestation proceedings involve several requests for relief, the Review Committee may terminate proceedings with regard to such requests in a single decision based on different grounds provided by subsection 1 of this section.

Amended by RT I, 05.05.2022, 2 (in force from 1 June 2022)

Want your procurement documents checked before publication? We will show you how Procurelex Verifika does it.

Request a demo

General information on the Public Procurement Act in force. Not legal advice.