Practical guide
Modifying a public contract during its term
A public contract may be changed after award without a new procurement only on the grounds of § 123 of the Public Procurement Act. This guide takes the contracting authority through those grounds step by step: review clauses, small modifications, additional purchases, unforeseeable circumstances, replacement of the contractor and non-substantial changes, followed by the register notices and termination.
Reviewed by Mara Ribeiro Duarte, Head of Public Sector at Closer · 20 November 2026
Legal basis§ 120(1) · § 123 · § 124 · § 123(1) · § 123(1) cl 1 · § 123(1) cl 2 · § 123(1) cl 3 · § 123(1) cl 4 · § 123(1) cl 5 · § 123(1) cl 6 · § 123(1) cl 7 · § 123(2) · § 123(2) cl 1 · § 123(2) cl 2 · § 123(2) cl 3 · § 123(2) cl 4 · § 123(3) · § 123(4) · § 123(5) · § 14(3) · § 14(4) · § 95 · § 95(1) · § 95(1) cl 5 · § 125(8) · § 126(10) · § 30(1) · § 219(3) · § 219(7) · § 219³ · § 23(7) · § 49(5) · § 83(7) · § 83(7) cl 1 · § 83(7) cl 2 · § 83(8) · § 124(1) cl 1 · § 124(1) cl 2 · § 124(1) cl 2¹ · § 124(1) cl 3 · § 124(1¹) cl 1 · § 124(1¹) cl 2 · § 124(1²) · § 179¹(1) cl 3 · § 124(2) · § 119 · official text
The starting point
A public contract is awarded on the terms set out in the procurement documents and in accordance with the successful tender (§ 120(1)). Changing those terms later is a matter for § 123: it lists the cases in which the contracting authority may modify a concluded contract without carrying out a new public procurement (§ 123(1)). A modification not permitted under § 123 gives the authority the right to terminate the contract or withdraw from it (§ 124(1) cl 1).
The same section governs modifications in the simple procedure (§ 125(8)) and in the specific procedure for social and other specific services (§ 126(10)). Contracts awarded under a framework agreement are awarded on its terms without substantially amending them (§ 30(1)); see the guide on framework agreements.
The grounds below are alternatives: one is enough. A short overview is in the FAQ on modifying a public contract; this guide walks through the questions in the order in which it may be practical to ask them.
Step 1: Did the procurement documents provide for it?
Review clauses. Regardless of its value, a modification is allowed where it does not alter the overall nature of the contract and its scope, substance and terms of application, for instance on the review of the price, were set out in the procurement documents in clear, precise and unequivocal clauses (§ 123(1) cl 2).
- The ground refers to the procurement documents, that is, the terms on which tenderers competed, not to terms agreed only afterwards.
- A general reservation of a right to amend the contract is unlikely to pass the test of clear, precise and unequivocal clauses. When drafting, it helps to state what may change, by how much and on what trigger.
A replacement clause. The economic operator may be replaced by another one if the procurement documents contained such a clause (§ 123(1) cl 5).
Step 2: Is the modification small?
A modification is allowed without a new procurement where the overall nature of the contract, for example its subject matter, is not altered and the total value of the modifications does not exceed (§ 123(1) cl 1):
- the international threshold under § 14(3) or, in defence and security, under § 14(4) (see the thresholds page); and
- ten per cent of the initial value of a supply or service contract, 15 per cent of the initial value of a works contract, or ten per cent of the initial value of a concession contract.
Both limits apply at once. The text speaks of the total value of the modifications, so the modifications are added together rather than assessed one by one. Where the contract contains an indexation clause, the calculation starts from the indexed value of the contract. Where a concession contract has no indexation clause, the indexed value is calculated from the average inflation in Estonia published by Statistics Estonia (§ 123(4)).
Step 3: Additional purchases or unforeseeable circumstances?
Additional supplies, services or works. The authority may buy from the same economic operator additional supplies, services or works that it has come to need and that the procurement documents did not include, where all of the following hold (§ 123(1) cl 3):
- a change of operator would cause the authority significant inconvenience or substantial additional costs; and
- it would be unreasonable for economic or technical reasons, for example because of interchangeability or interoperability with existing supplies, services or installations; and
- no modification increases the value of the contract by more than 50 per cent of its initial value.
Unforeseeable circumstances. A modification is allowed where it is caused by circumstances that a diligent authority could not foresee, the overall nature of the contract is not altered and no modification increases its value by more than 50 per cent of its initial value (§ 123(1) cl 4).
For both grounds:
- The 50 per cent limit is measured against the initial value, or the indexed value where there is an indexation clause (§ 123(4)). The Estonian text applies it to each modification ("ühegi muudatuse tulemusena").
- The limit does not apply to procurements in the network sector or to concession contracts in the fields of activity listed in Annex II to Directive 2014/23/EU (§ 123(3)).
- A modification notice must be filed with the register (see below).
The ground in § 123(1) cl 4 turns on what a diligent authority could have foreseen. A practical way to show this is to keep a written record, at the time of the modification, of what happened, when, and why it could not have been anticipated during the procurement.
Step 4: Is the contractor being replaced?
The Act names two cases in which a new contractor may take over the contract:
- the procurement documents contained a replacement clause (§ 123(1) cl 5); or
- the contractor is restructured, including by takeover, merger, transfer or insolvency, and is wholly or partly replaced by a new operator that would not be excluded under § 95, meets the selection criteria in the procurement documents, and the replacement brings no other substantial changes to the contract (§ 123(1) cl 6).
Any other replacement of the economic operator is a substantial modification (§ 123(2) cl 4).
Step 5: Is the change substantial at all?
Whatever its value, a modification is allowed if it is not substantial (§ 123(1) cl 7). A modification is substantial where it alters the overall nature of the contract considerably, in particular where (§ 123(2)):
- it introduces a condition that, had it been in the procurement documents, would have attracted additional participants or increased the number of tenders to be declared suitable (§ 123(2) cl 1);
- it shifts the balance of the contractual obligations in favour of the economic operator in a way the contract does not provide for (§ 123(2) cl 2);
- it considerably extends the scope of the subject matter of the contract (§ 123(2) cl 3);
- it replaces the economic operator other than under § 123(1) cl 5 or § 123(1) cl 6 (§ 123(2) cl 4).
The list is not closed ("in particular"). A useful check is to ask of each change whether the competition would have looked different had the change been in the documents from the start, and whether it gives the contractor something the contract did not promise.
If no ground fits
Then the change needs a new procurement. The Act does offer a route for repeating similar services or works with the same tenderer through a negotiated procedure without prior publication, but only within three years of the original contract, in conformity with the basic project, and only where the original contract notice announced that possibility, its scope and terms (§ 49(5)); the value of such services or works is then included in the original estimated value (§ 23(7)). See the guide on the negotiated procedure without prior publication and the guide on estimated value.
Notices to the register
- Additional purchases and unforeseeable circumstances. For a modification under § 123(1) cl 3 or § 123(1) cl 4, the authority files a contract modification notice with the register within 30 days of making it. This does not apply to a contract awarded under a framework agreement (§ 123(5)).
- At the end of the contract. Within 30 days after the contract is completed, the authority files its actual value (§ 83(7) cl 1) and the modifications for which no modification notice was filed (§ 83(7) cl 2) (§ 83(7)). For a framework agreement, the period runs from the completion of the agreement or of the last contract under it, whichever is later (§ 83(8)).
Modifications under the other grounds are therefore reported once, at the end. Keeping a running log of every modification and the ground relied on makes that final report straightforward.
Termination and withdrawal
The authority may terminate or withdraw from the contract where:
- modifications not permitted under § 123 have been made (§ 124(1) cl 1);
- at the time of award, one of the grounds in clauses 1–4 of § 95(1) applied to the contractor, which should have been excluded or should not have been awarded the contract (§ 124(1) cl 2), or such a ground applies during performance (§ 124(1) cl 2¹);
- the Court of Justice of the European Union has found, in proceedings under Article 258 TFEU, that obligations under the Treaty or under Directive 2014/23/EU, 2014/24/EU or 2014/25/EU were breached in the procurement or the award (§ 124(1) cl 3).
The authority must terminate or withdraw where the sanctions ground of § 95(1) cl 5 applied to the contractor at award or at any time after it (§ 124(1¹) cl 1), or where continuing performance would breach an international sanction or a sanction of the Government (§ 124(1¹) cl 2). It then notifies the Financial Intelligence Unit (§ 124(1²)) within three working days (§ 179¹(1) cl 3).
Where the contract was concluded by acceptance and the tenderer does not start performance within the time set, the authority may terminate early or withdraw and apply § 119 (§ 124(2)).
Older contracts
For contracts awarded under the earlier Public Procurement Act, modification is governed by § 123 (§ 219(3)) and termination by § 124 (§ 219(7)). Procurement proceedings started before 1 November 2026 are completed under the version of the Act in force until 31 October 2026 (§ 219³); the FAQ explains what that provision does and does not say about modifications. This guide does not cover case law or remedies against modifications.
Related pages
Previous guide
Abnormally low tenders and the rejection of all tenders
Next guide
Conflict of interest in public procurement