Text of the consolidated version in force from 1 November 2026 (RT I, 03.07.2026, 7). Where this page and Riigi Teataja differ, Riigi Teataja prevails: official textOfficial English translation (it renders the version of 1 October 2026)The Estonian text is the only one with legal force; the English is a translation.

† Our own working translation of words that the reform of 1 November 2026 changed: Riigi Teataja has not yet published an official English text of them, and replaces ours when it does.

(1) The contracting authority or entity has a right to modify a public contract without carrying out new public procurement where:

1) the overall nature of the public contract, for example, the subject matter of the public contract is not altered and the total value of the modifications does not exceed the limit provided by subsection 3 or 4 of § 14 of this Act or ten per cent of the initial cost of the supplies or services or 15 per cent of the initial cost of the contract for works or ten per cent of the initial value of the concession contract;

2) regardless of the value of the modification, the overall nature of the public contract is not altered and the scope, substance and terms of application of the modification, for instance, regarding the review of the price, were provided by the procurement documents in clear, precise and unequivocal clauses;

3) additional supplies, services or works that the authority or entity needs but that were not specified in the procurement documents are purchased from the same economic operator, if switching the tenderer would cause significant inconvenience or substantial additional costs for the authority or entity, and would be unreasonable for economic or technical reasons such as requirements of interchangeability or interoperability with supplies, services, or installations, provided that any increase in value resulting from any modifications does not exceed 50 per cent of the original value of the public contract;†

Changed 1 November 2026
Wording until 31 October 2026

additional supplies, services or works that the authority or entity needs but that were not specified in the procurement documents are purchased from the same economic operator, if switching the tenderer would cause significant inconvenience or substantial additional costs for the authority or entity, and could not be made for economic or technical reasons such as requirements of interchangeability or interoperability with supplies, services, or installations, provided that any increase in value resulting from any modifications does not exceed 50 per cent of the original value of the public contract;

4) the modification is caused by circumstances unforeseeable to a diligent authority or entity, and the overall nature of the public contract is not altered and, as a result of any modification, the value of the public contract does not increase by more than 50 per cent of its original value;

5) an economic operator is replaced by another one, if the procurement documents contained the corresponding modification clause;

6) due to an economic operator’s reorganisation – including takeover, merger, transfer or insolvency – the operator is partly or entirely replaced by a new one who would not be subject to exclusion under § 95 of this Act and who fulfils the selection criteria established in the procurement documents, provided such a replacement does not entail other substantial changes to the public contract;

7) irrespective of its value, the modification is not substantial.

(2) A modification is considered to be substantial for the purposes of this section where the overall nature of the public contract is altered substantially, in particular, where:

1) the modification introduces a condition which, had it been part of the procurement documents, would have attracted additional participants in the procurement procedure or increased the number of tenders to be declared suitable;

2) the modification results in a change in the balance of mutual contractual obligations arising from the public contract in favour of the economic operator in a way not provided for by the public contract;

3) the modification extends the scope of the subject matter of the public contract considerably;

4) an economic operator is replaced with a new one in a situation other than those mentioned in clause 5 or 6 of subsection 1 of this section.

(3) The value threshold of a modification provided for by clauses 3 and 4 of subsection 1 of this section does not apply to public procurements in the network sector or to concession contracts in the fields of activity mentioned in Annex II to Directive 2014/23/EU of the European Parliament and of the Council.

(4) Where the public contract includes an indexation clause, the value mentioned in clauses 1, 3 and 4 of subsection 1 of this section is calculated based on the indexed value of the contract. Where the concession contract lacks an indexation clause, the indexed value of the public contract is calculated based on the average inflation in Estonia as published by the Estonian Statistical Office.

(5) Regarding a modification made under clause 3 or 4 of subsection 1 of this section, the contracting authority or entity files a public contract modification notice with the register within 30 days following the making of the modification, except where the contract that was modified had been awarded under a framework agreement.†

Changed 1 November 2026
Wording until 31 October 2026

Regarding a modification made under clause 3 or 4 of subsection 1 of this section, the contracting authority or entity files a public contract modification notice with the register within ten days following the making of the modification, except where the contract that was modified had been awarded under a framework agreement.

The section as it read until 31 October 2026

(1) The contracting authority or entity has a right to modify a public contract without carrying out new public procurement where:

1) the overall nature of the public contract, for example, the subject matter of the public contract is not altered and the total value of the modifications does not exceed the limit provided by subsection 3 or 4 of § 14 of this Act or ten per cent of the initial cost of the supplies or services or 15 per cent of the initial cost of the contract for works or ten per cent of the initial value of the concession contract;

2) regardless of the value of the modification, the overall nature of the public contract is not altered and the scope, substance and terms of application of the modification, for instance, regarding the review of the price, were provided by the procurement documents in clear, precise and unequivocal clauses;

3) additional supplies, services or works that the authority or entity needs but that were not specified in the procurement documents are purchased from the same economic operator, if switching the tenderer would cause significant inconvenience or substantial additional costs for the authority or entity, and could not be made for economic or technical reasons such as requirements of interchangeability or interoperability with supplies, services, or installations, provided that any increase in value resulting from any modifications does not exceed 50 per cent of the original value of the public contract;

4) the modification is caused by circumstances unforeseeable to a diligent authority or entity, and the overall nature of the public contract is not altered and, as a result of any modification, the value of the public contract does not increase by more than 50 per cent of its original value;

5) an economic operator is replaced by another one, if the procurement documents contained the corresponding modification clause;

6) due to an economic operator’s reorganisation – including takeover, merger, transfer or insolvency – the operator is partly or entirely replaced by a new one who would not be subject to exclusion under § 95 of this Act and who fulfils the selection criteria established in the procurement documents, provided such a replacement does not entail other substantial changes to the public contract;

7) irrespective of its value, the modification is not substantial.

(2) A modification is considered to be substantial for the purposes of this section where the overall nature of the public contract is altered substantially, in particular, where:

1) the modification introduces a condition which, had it been part of the procurement documents, would have attracted additional participants in the procurement procedure or increased the number of tenders to be declared suitable;

2) the modification results in a change in the balance of mutual contractual obligations arising from the public contract in favour of the economic operator in a way not provided for by the public contract;

3) the modification extends the scope of the subject matter of the public contract considerably;

4) an economic operator is replaced with a new one in a situation other than those mentioned in clause 5 or 6 of subsection 1 of this section.

(3) The value threshold of a modification provided for by clauses 3 and 4 of subsection 1 of this section does not apply to public procurements in the network sector or to concession contracts in the fields of activity mentioned in Annex II to Directive 2014/23/EU of the European Parliament and of the Council.

(4) Where the public contract includes an indexation clause, the value mentioned in clauses 1, 3 and 4 of subsection 1 of this section is calculated based on the indexed value of the contract. Where the concession contract lacks an indexation clause, the indexed value of the public contract is calculated based on the average inflation in Estonia as published by the Estonian Statistical Office.

(5) Regarding a modification made under clause 3 or 4 of subsection 1 of this section, the contracting authority or entity files a public contract modification notice with the register within ten days following the making of the modification, except where the contract that was modified had been awarded under a framework agreement.

Amended by RT I, 05.05.2022, 2 (in force from 1 June 2022) · RT I, 03.07.2026, 3 (in force from 1 November 2026)

Cross-references

This section refers to

Want your procurement documents checked before publication? We will show you how Procurelex Verifika does it.

Request a demo

General information on the Public Procurement Act in force. Not legal advice.