Procurement rules (hankekord), the procurement plan and preparing a procurement

Which contracting authorities must establish internal procurement rules, what the rules and the annual procurement plan must cover and how they are published, and how market consultations and the prior involvement of economic operators are handled.

Updated 19 November 2026

Reviewed by Mara Ribeiro Duarte, Head of Public Sector at Closer · 20 November 2026

Legal basis§ 9(1) · § 9(2) · § 9(3) · § 9(4) · § 9(4) cl 1 · § 9(4) cl 2 · § 9(4) cl 3 · § 9(4) cl 4 · § 9(4) cl 4¹ · § 9(4) cl 5 · § 9(4) cl 6 · § 9(5) · § 9(6) · § 9(7) · § 9(8) · § 3 · § 3 cl 1 · § 3 cl 2 · § 3 cl 3 · § 3 cl 4 · § 3 cl 5 · § 10(1) · § 10(2) · § 10(3) · § 10(3) cl 1 · § 10(3) cl 2 · § 10(3¹) · § 10(4) · § 95(4) · § 95(4) cl 7 · § 42(1) · § 42(8) · § 42(11) · § 43(1) · § 43(3) · § 43(4) · official text

Who must establish procurement rules

The Public Procurement Act requires internal procurement rules (hankekord) from a contracting authority or entity whose planned procurements in a budgetary year are large enough. The test is the estimated total value of the procurements it envisages for that year:

  • Contracting authorities. Rules are required where the estimated total value of the envisaged public procurements of supplies and services exceeds 80 000 euros, or that of public works exceeds 500 000 euros (§ 9(1)).
  • Contracting entities in the network sector. Rules are required where the estimated total value of all their envisaged public procurements in a budgetary year exceeds 500 000 euros (§ 9(2)).
  • Rules for a group of authorities. A minister in charge of a policy sector may establish procurement rules and a procurement plan for the contracting authorities of the ministry's area of government, a local authority for its agencies, and a contracting entity in the network sector for the contracting entities within its group (§ 9(3)).

The figures are totals for the year, not the value of a single contract. How the value of each procurement is estimated is explained in the guide on estimated value.

What the procurement rules must contain

The rules provide for, among other things (§ 9(4)):

  • Planning. The rules for planning public procurement, including the rules and the closing date for drawing up and approving the annual procurement plan (§ 9(4) cl 1).
  • Responsible persons. The appointment of a person responsible for the public procurement, including the person responsible for the performance of the public contract (§ 9(4) cl 2).
  • Purchases below the simple threshold. The rules for purchasing supplies, services and works below the simple procurement threshold (§ 9(4) cl 3). What else applies to such purchases is in the FAQ on purchases below the threshold.
  • Special services. Where needed, the rules for purchasing social and other specific services, including those below their own simple procurement threshold, except in the fields of defence and security (§ 9(4) cl 4); and, where needed, the rules for awarding public contracts under the simplified procedure of § 152¹ (§ 9(4) cl 4¹).
  • Defence and security. Where needed, the light regime for buying services in the fields of defence and security, including services below the threshold for that regime (§ 9(4) cl 5).
  • Conflict of interest. Measures for preventing, identifying and remedying a conflict of interest in public procurement, unless another internal document on work organisation already provides them (§ 9(4) cl 6).

The words "among other things" mean the list is a minimum: the authority may regulate other matters in its rules as well.

Conflict of interest measures without procurement rules

An authority or entity that is not required to establish procurement rules must still set out measures for preventing, identifying and remedying a conflict of interest. It does so in an internal document on work organisation or, if it chooses to establish procurement rules, in those rules (§ 9(5)). This follows from the general principle that the authority avoids a competition-distorting conflict of interest (§ 3 cl 4).

The procurement plan

The Act does not list the contents of the annual procurement plan (hankeplaan). It requires the procurement rules to lay down how and by what date the plan is drawn up and approved (§ 9(4) cl 1), and the authority publishes the plan on its website without delay after approving it (§ 9(8)).

Publication

  • Both documents are public. The procurement rules and the procurement plan are public (§ 9(6)).
  • Conflict of interest measures. Where the measures of § 9(5) are set out in an internal document on work organisation, the respective part of that document must be public (§ 9(6)).
  • Website and register. The authority publishes the procurement rules, or the other internal document or its relevant part, on its website without delay after establishing or amending them, and publishes a reference to its website in the register (§ 9(7)).

The general principles

When carrying out public procurement, the authority follows the principles of § 3. The contracting authority or entity:

  • Transparency. acts transparently, verifiably and proportionately (§ 3 cl 1);
  • Equal treatment. treats equally all persons whose place of residence or seat is in Estonia, in another Member State of the European Union, in another contracting state of the European Economic Area or in a country that has joined the Government Procurement Agreement of the World Trade Organization, and makes certain that all restrictions and criteria imposed on them are proportional, relevant and reasoned in relation to the purpose of the procurement (§ 3 cl 2);
  • Competition. ensures effective use of competition, so that the participation of a public legal person or a private legal person using public funds does not distort competition because of its use of public funds (§ 3 cl 3);
  • Conflict of interest. avoids a competition-distorting conflict of interest (§ 3 cl 4);
  • Economy. uses funds economically and expediently, awards the public contract based on the best price-quality ratio and carries out the procurement within a reasonable time (§ 3 cl 5).

Market consultation before the procedure

Before commencing procurement proceedings, the authority may conduct a market consultation (turu-uuring) to prepare the procurement and to inform economic operators of the planned procurement and of the requirements it will contain (§ 10(1)). The Act allows it; it does not require it.

During the consultation the authority may consult persons and economic operators operating in the relevant field. It may use the advice in planning and carrying out the procurement, provided that this does not distort competition. If it uses the advice in the procurement proceedings, it ensures that the principles of equal treatment and transparency are observed (§ 10(2)).

When an economic operator was involved in the preparation

Where an economic operator took part in the market consultation or was otherwise involved in preparing the procurement, the authority takes measures to prevent the distortion of competition, including (§ 10(3)):

  • Sharing the information. stating in the procurement documents any significant information exchanged with that operator in connection with preparing the procurement (§ 10(3) cl 1);
  • Time limit. setting a time limit for tenders or requests to participate long enough that the operator gains no advantage over others from its prior knowledge (§ 10(3) cl 2).

The authority does not disclose the trade secrets of that operator in the procurement documents (§ 10(3¹)).

Involvement in the preparation does not by itself exclude the operator. Where an operator's tender or request was prepared with the involvement of a person who took part in preparing the same procurement or is otherwise related to the authority, the information this gives an advantage over other participants, and the distortion of competition cannot be avoided by other means, the authority may exclude it on the ground in § 95(4) cl 7, an optional ground that the authority can apply only if the procurement documents provide for it (§ 95(4)). Before applying that ground, where its measures do not ensure equal treatment, the authority must give the operator a reasonable time to explain and prove that its involvement does not distort competition (§ 10(4)).

Central and joint procurement

When planning, an authority may decide not to procure on its own. It may join a public procurement carried out by a central purchasing body by an agreement with that body (§ 42(1), § 42(8)), and is then responsible only for the stages or operations it carries out itself (§ 42(11)). Two or more authorities may also carry out a joint procurement, where one of them is authorised to procure for the others (§ 43(1)); they bear joint and several liability for compliance with the Act for what is done jointly, and each is solely liable for what it does on its own (§ 43(3), § 43(4)).

The procedures that follow are explained in the guide on the simple procedure and the guide on technical specifications; what the procurement documents must contain is in the FAQ on procurement documents. This guide repeats the wording of the Act; it does not offer a model text of procurement rules or cover the appointment of central purchasing bodies by the Government, a minister or a local authority.

Want your procurement documents checked before publication? We will show you how Procurelex Verifika does it.

Request a demo

General information on the Public Procurement Act in force. Not legal advice.