These answers describe the Act as in force from 1 November 2026. For a contracting authority in the public sector, the estimated value of a procurement decides the rules: the simple procedure applies from the simple procurement threshold up to the international threshold, the rules of Chapter 2 apply from the international threshold, and below the simple threshold the Act prescribes no procedure of its own (§ 15(1), § 15(2)). Procurements started before 1 November 2026 are completed under the version of the Act that applied until 31 October 2026 (§ 219³). The thresholds page lists the current figures and their legal basis.

What are the simple procurement threshold and the international threshold?

The simple procurement threshold depends on the subject of the contract: 50 000 euros for supplies or services contracts (§ 14(1) cl 1); 100 000 euros for works contracts, service concession contracts, supplies or services contracts in defence and security (except services ordered under the light regime) and supplies or services contracts of a contracting entity operating in the network sector (§ 14(1) cl 2); 500 000 euros for works contracts in defence and security and of a contracting entity operating in the network sector (§ 14(1) cl 3); 100 000 euros for contracts and concession contracts for specific services and for design contests (§ 14(1) cl 4); and 500 000 euros for contracts and concession contracts for social services (§ 14(1) cl 5). All values exclude VAT (§ 23(1)). The international threshold is not a figure in the Act: it is set periodically by the European Commission and published in the Official Journal of the European Union (§ 14(3); for defence and security § 14(4)). The values currently applied are on the thresholds page.

Legal basis§ 14(1) cl 1 · § 14(1) cl 2 · § 14(1) cl 3 · § 14(1) cl 4 · § 14(1) cl 5 · § 23(1) · § 14(3) · § 14(4) · official text

Which rules apply at which estimated value?

A contracting authority in the public sector applies the simple procedure where the estimated value of the contract equals or exceeds the simple threshold but is below the international threshold (§ 15(1)), and the rules of Chapter 2 where it equals or exceeds the international threshold (§ 15(2)). For social and other specific services it applies the specific procedure (§ 126) from the simple threshold for those services (§ 15(3)). A contracting entity operating in the network sector applies the simplified award procedure (§ 152¹) between the two thresholds (§ 15(9¹)) and the rules of Chapter 5 from the international threshold, where the main purpose of the contract relates to its network-sector activities or cannot be determined (§ 15(9)). In defence and security the simple procedure applies from the simple threshold up to the international threshold (§ 15(4)) and the rules of Chapter 6 from the international threshold for those fields (§ 15(5)). For purchases below the simple threshold see procurements below the threshold.

Legal basis§ 15(1) · § 15(2) · § 126 · § 15(3) · § 152¹ · § 15(9¹) · § 15(9) · § 15(4) · § 15(5) · official text

How is the procedure chosen?

Under the rules of Chapter 2 the contracting authority must use the open or restricted procedure unless the Act provides otherwise (§ 48(1)). It may set up an innovation partnership where it needs innovative supplies, services or works that existing market solutions cannot meet (§ 48(2)). A competitive procedure with negotiation or a competitive dialogue may be used only on the grounds listed in § 48(3), for example where the estimated value is below the international threshold (§ 48(3) cl 1), all tenders submitted in an open or restricted procedure were unacceptable (§ 48(3) cl 2) or the contract includes the purchase of a design service or the development of innovative solutions (§ 48(3) cl 5). The cases in which a negotiated procedure without prior publication may be used are set out in § 49 and § 50. In the simple procedure the authority sets the rules in the procurement documents and may also rely on other provisions of the Act (§ 125(2)); it may provide for successive stages or negotiations (§ 125(6)). See the guide to the simple procedure.

Legal basis§ 48(1) · § 48(2) · § 48(3) · § 48(3) cl 1 · § 48(3) cl 2 · § 48(3) cl 5 · § 49 · § 50 · § 125(2) · § 125(6) · official text

How is the estimated value determined?

All estimated values in the Act are calculated excluding VAT (§ 23(1)). The estimated value covers the total amount expected to be paid under the contract, including possible future obligations and renewal of the contract (§ 23(2) cl 1), and is based on the price level corresponding to the average market price immediately before the procurement starts (§ 23(3)). For a framework agreement it is the maximum total value of the contracts to be awarded under it during its validity (§ 23(4)). The basis of calculation may not be chosen in order to avoid the rules, and where several methods are possible and one of them gives a value at or above a threshold, that method is used (§ 23(8)). A procurement may not be divided into lots in order to avoid the rules of the Act (§ 28(2)).

Legal basis§ 23(1) · § 23(2) cl 1 · § 23(3) · § 23(4) · § 23(8) · § 28(2) · official text

May an authority apply the Act’s procedures although the threshold is not reached?

Yes. The contracting authority has the right to apply the mandatory procedure of the Act also to a contract whose estimated value does not reach the threshold concerned (§ 15(11)). If it starts a procurement in the register without being obliged to by law, it must follow the procedural rules of the Act (§ 15(12)).

Legal basis§ 15(11) · § 15(12) · official text

Who carries out the procurement?

A central purchasing body may carry out centralised procurement for authorities (§ 42(1)); the Government, a minister within the area of government of the ministry and a local authority within its area may each appoint one (§ 42(2), § 42(5), § 42(7¹)), and an authority may join a procurement run by it by agreement (§ 42(8)). The Government may decide that an authority does not carry out procurements on its own or jointly to the extent it determines (§ 42(3)); this does not apply to constitutional institutions, public legal persons, private legal persons acting as contracting authorities or local authorities (§ 42(4)). In a joint procurement one participating authority carries out the procurement for the others on the basis of an agreement (§ 43(1)), and the authorities are jointly and severally liable for adherence to the Act where it is carried out fully in their common interest (§ 43(3)).

Legal basis§ 42(1) · § 42(2) · § 42(5) · § 42(7¹) · § 42(8) · § 42(3) · § 42(4) · § 43(1) · § 43(3) · official text

What changed on 1 November 2026?

From 1 November 2026 the Act no longer has a national threshold, the ‘public procurement threshold’: only the simple procurement threshold and the international threshold remain (§ 14(1), § 14(3)). For a contracting authority in the public sector the rules of Chapter 2 are now mandatory only from the international threshold (§ 15(2)), and between the two thresholds the simple procedure applies (§ 15(1)). The simple thresholds were raised (§ 14(1) cl 1, § 14(1) cl 2), and a simplified award procedure was added for contracting entities operating in the network sector (§ 152¹). Several periods in the simple procedure were lengthened as well, for example the minimum time limit for tenders and the standstill period (§ 125(4), § 125(9)); see time limits. Procurements started before 1 November 2026 are completed under the version of the Act in force until 31 October 2026 (§ 219³); in that version the simple threshold for supplies and services was 30 000 euros (works 60 000 euros) and the national threshold 60 000 euros (works 150 000 euros). See also the guide to the 2026 reform.

Legal basis§ 14(1) · § 14(3) · § 15(2) · § 15(1) · § 14(1) cl 1 · § 14(1) cl 2 · § 152¹ · § 125(4) · § 125(9) · § 219³ · official text