Public Procurement Act · Chapter 2
§ 122. Subcontracting
Chapter 2 · Procurement Procedure · Division 5: Award and Performance of Public Contract
Changed 1 November 2026
† Our own working translation of words that the reform of 1 November 2026 changed: Riigi Teataja has not yet published an official English text of them, and replaces ours when it does.
(1) In the procurement documents, the contracting authority or entity may require the tenderer to indicate the proportion and nature of the lot of the public contract which the tenderer intends to subcontract, along with the names of the planned subcontractors.
(2) In the case of a public works contract or works concession whose estimated value is at least 500 000 euros and in the case of a public service contract which involves services provided on site under direct supervision of the contracting authority or entity and whose estimated value equals or exceeds the international threshold, the authority or entity requires in the procurement documents that the tenderer who has been awarded the public contract submit to the authority or entity at the latest by the time of commencement of performance of the public contract the names and contact particulars as well as particulars of statutory representatives of any subcontractors who are known at that time to participate in the performance of the contract. The authority or entity also requires submission of the same information regarding each subcontractor who participates in the performance of the works contract or works concession and regarding whom information has not been submitted to the authority or entity by the time of commencement of performance of the contract.†
Wording until 31 October 2026
In the case of a public works contract or works concession whose estimated value equals or exceeds the public procurement threshold and in the case of a public service contract which involves services provided on site under direct supervision of the contracting authority or entity and whose estimated value equals or exceeds the international threshold, the authority or entity requires in the procurement documents that the tenderer who has been awarded the public contract submit to the authority or entity at the latest by the time of commencement of performance of the public contract the names and contact particulars as well as particulars of statutory representatives of any subcontractors who are known at that time to participate in the performance of the contract. The authority or entity also requires submission of the same information regarding each subcontractor who participates in the performance of the works contract or works concession and regarding whom information has not been submitted to the authority or entity by the time of commencement of performance of the contract.
(3) In the case of a public works contract or works concession whose estimated value is at least 500 000 euros, the contracting authority or entity requires in the procurement documents that the tenderer warrant in their tender that they will not enlist, in the performance of the contract, a subcontractor who would be subject to replacement under subsection 7 of this section.†
Wording until 31 October 2026
In the case of a public works contract or works concession, the contracting authority or entity requires in the procurement documents that the tenderer warrant in their tender that they will not enlist, in the performance of the contract, a subcontractor who would be subject to replacement under subsection 7 of this section.
(4) When applying subsections 1, 2 and 11 of this section, the contracting authority or entity may verify the inapplicability of grounds for exclusion regarding the subcontractors and whether they meet the selection criteria in accordance with the provisions of this Act during the procurement procedure or after awarding the public contract where the authority or entity has indicated such possibility and conditions in the procurement documents.
(5) In the case of a public works contract or works concession whose estimated value is at least 500 000 euros, the contracting authority or entity verifies, during procurement proceedings, the inapplicability of grounds for exclusion mentioned in subsection 1 of § 95 of this Act – or, in the fields of defence and security, in clauses 1, 4 or 5 of subsection 1 of § 95 – regarding the subcontractors mentioned in the successful tenderer’s tender and, following the award of the contract, regarding any subcontractor who is added in the course of its performance and whose share of the value of the public contract is at least ten per cent. Such verification is not required in a negotiated procedure without prior publication or during performance of the contract awarded as a result of that procedure.†
Wording until 31 October 2026
In the case of a public works contract or works concession, the contracting authority or entity verifies, during procurement proceedings, the inapplicability of grounds for exclusion mentioned in subsection 1 of § 95 of this Act – or, in the fields of defence and security, in clauses 1, 4 or 5 of that subsection – regarding the subcontractors mentioned in the successful tenderer’s tender and, following the award of the contract, regarding any subcontractor who is added in the course of its performance. Such verification is not required in a negotiated procedure without prior publication or during performance of the contract awarded as a result of that procedure.
(6) When verifying the grounds for exclusion based on subsection 5 of this section, the contracting authority or entity applies subsections 2–4 of § 96 of this Act. The authority or entity does not require documents to be submitted in order to verify the inapplicability of grounds for exclusion where such documents or the corresponding particulars are available free of charge to the authority or entity based on information in a database or where the authority or entity possesses the documents or particulars and these remain relevant for verifying the inapplicability of grounds for exclusion regarding a subcontractor.
(7) Where the contracting authority or entity, when it conducts a verification of the inapplicability of grounds for exclusion regarding a subcontractor, ascertains that, regarding the subcontractor, the grounds provided by subsection 1 of § 95 of this Act – or, in the fields of defence and security, the grounds provided by clauses 1, 4 or 5 of that subsection – apply, the authority or entity requires the subcontractor to be replaced. Where the ground provided by subsection 4 of § 95 – or, in the fields of defence and security, the grounds provided by clauses 3 or 4 of that subsection, or by subsection 2 of § 177 – applies regarding the subcontractor, the authority or entity may require that the subcontractor be replaced. If the tenderer has been required to replace a subcontractor but does not do so, the authority or entity rejects the tender, unless the tenderer warrants that it will perform the relevant part of the contract itself.
(7¹) Where the contracting authority or entity, during procurement proceedings or during performance of the public contract, ascertains that, regarding a subcontractor, the grounds provided by clause 4 of subsection 1 of § 95 of this Act – or, where subsection 4¹ is applied, the ground provided by that subsection – apply, the authority or entity grants the subcontractor, through the tenderer, once during the procurement procedure, a period of at least three working days to settle the tax debt or obtain a deferral. Where valid reasons are present, the authority or entity may extend the time limit or repeatedly give an opportunity to settle the tax debt or obtain a deferral. If the subcontractor has, by the due date set by the authority or entity, settled the tax debt or obtained a deferral, the authority or entity does not apply the provisions of subsection 7 of this section.†
Wording until 31 October 2026
Where the contracting authority or entity, during procurement proceedings or during performance of the public contract, ascertains that, regarding a subcontractor, the grounds provided by clause 4 of subsection 1 of § 95 of this Act – or, where subsection 4¹ is applied, the ground provided by that subsection – apply, the authority or entity grants the subcontractor, through the tenderer, a period of at least three days to settle the tax debt or obtain a deferral. Where valid reasons are present, the authority or entity may extend the time limit. If the subcontractor has, by the due date set by the authority or entity, settled the tax debt or obtained a deferral, the authority or entity does not apply the provisions of subsection 7 of this section.
(8) In the case of a public works contract or works concession whose estimated value is at least 500 000 euros, the contracting authority or entity, based on a request for information filed by a subcontractor who participated in the performance of the contract, presents to the subcontractor information on whether the tenderer has been remunerated for proven works performed by the subcontractor to the extent that the tenderer is required to remunerate the subcontractor. In the request, the subcontractor files with the authority or entity proof of existence of the sub-contract, the amount of the claim and whether the claim has fallen due. The authority or entity informs the tenderer without delay of the filing of the request and transmits a copy to the tenderer along with enclosed evidence and the information presented to the subcontractor.†
Wording until 31 October 2026
In the case of a public works contract or works concession whose estimated value equals or exceeds the public procurement threshold, the contracting authority or entity, based on a request for information filed by a subcontractor who participated in the performance of the contract, presents to the subcontractor information on whether the tenderer has been remunerated for proven works performed by the subcontractor to the extent that the tenderer is required to remunerate the subcontractor. In the request, the subcontractor files with the authority or entity proof of existence of the sub-contract, the amount of the claim and whether the claim has fallen due. The authority or entity informs the tenderer without delay of the filing of the request and transmits a copy to the tenderer along with enclosed evidence and the information presented to the subcontractor.
(9) In the case of a public works contract or works concession whose estimated value is at least 500 000 euros, where a subcontractor who participated in the performance of the contract or concession files with the contracting authority or entity a reasoned application in connection with groundless non-performance of a financial obligation by the tenderer under the subcontract concluded with the subcontractor, the authority or entity may decide not to perform a corresponding part of the financial claim presented to it by the tenderer under the contract or concession. In such a situation, the authority or entity performs the financial obligation to the tenderer once the financial obligation to the subcontractor has been performed or evidence showing the subcontractor’s claim to be unfounded has been filed with the authority or entity.†
Wording until 31 October 2026
In the case of a public works contract or works concession whose estimated value equals or exceeds the public procurement threshold, where a subcontractor who participated in the performance of the contract or concession files with the contracting authority or entity a reasoned application in connection with groundless non-performance of a financial obligation by the tenderer under the subcontract concluded with the subcontractor, the authority or entity decides not to perform a corresponding part of the financial claim presented to it by the tenderer under the contract or concession. The authority or entity performs the financial obligation to the tenderer once the financial obligation to the subcontractor has been performed or evidence showing the subcontractor’s claim to be unfounded has been filed with the authority or entity.
(10) Non-performance of a financial obligation towards the tenderer based on an application of the subcontractor mentioned in subsection 9 of this section is not deemed a breach of the public contract by the contracting authority or entity.
(11) Where the contracting authority or entity provides for such possibility and relevant conditions in the procurement documents, the authority or entity may apply this section also in the case of:
1) public supply contracts;
2) public service contracts, where the services are not provided on site under the direct supervision of the authority or entity;
3) subcontracts concluded for the purchasing or delivery of supplies required for execution of works or provision of services;
4) subcontracts concluded by subcontractors;†
Wording until 31 October 2026
subcontracts concluded by subcontractors.
5) subcontractors to whom the verification mentioned in subsection 5 of this section does not extend.†
The section as it read until 31 October 2026
(1) In the procurement documents, the contracting authority or entity may require the tenderer to indicate the proportion and nature of the lot of the public contract which the tenderer intends to subcontract, along with the names of the planned subcontractors.
(2) In the case of a public works contract or works concession whose estimated value equals or exceeds the public procurement threshold and in the case of a public service contract which involves services provided on site under direct supervision of the contracting authority or entity and whose estimated value equals or exceeds the international threshold, the authority or entity requires in the procurement documents that the tenderer who has been awarded the public contract submit to the authority or entity at the latest by the time of commencement of performance of the public contract the names and contact particulars as well as particulars of statutory representatives of any subcontractors who are known at that time to participate in the performance of the contract. The authority or entity also requires submission of the same information regarding each subcontractor who participates in the performance of the works contract or works concession and regarding whom information has not been submitted to the authority or entity by the time of commencement of performance of the contract.
(3) In the case of a public works contract or works concession, the contracting authority or entity requires in the procurement documents that the tenderer warrant in their tender that they will not enlist, in the performance of the contract, a subcontractor who would be subject to replacement under subsection 7 of this section.
(4) When applying subsections 1, 2 and 11 of this section, the contracting authority or entity may verify the inapplicability of grounds for exclusion regarding the subcontractors and whether they meet the selection criteria in accordance with the provisions of this Act during the procurement procedure or after awarding the public contract where the authority or entity has indicated such possibility and conditions in the procurement documents.
(5) In the case of a public works contract or works concession, the contracting authority or entity verifies, during procurement proceedings, the inapplicability of grounds for exclusion mentioned in subsection 1 of § 95 of this Act – or, in the fields of defence and security, in clauses 1, 4 or 5 of that subsection – regarding the subcontractors mentioned in the successful tenderer’s tender and, following the award of the contract, regarding any subcontractor who is added in the course of its performance. Such verification is not required in a negotiated procedure without prior publication or during performance of the contract awarded as a result of that procedure.
(6) When verifying the grounds for exclusion based on subsection 5 of this section, the contracting authority or entity applies subsections 2–4 of § 96 of this Act. The authority or entity does not require documents to be submitted in order to verify the inapplicability of grounds for exclusion where such documents or the corresponding particulars are available free of charge to the authority or entity based on information in a database or where the authority or entity possesses the documents or particulars and these remain relevant for verifying the inapplicability of grounds for exclusion regarding a subcontractor.
(7) Where the contracting authority or entity, when it conducts a verification of the inapplicability of grounds for exclusion regarding a subcontractor, ascertains that, regarding the subcontractor, the grounds provided by subsection 1 of § 95 of this Act – or, in the fields of defence and security, the grounds provided by clauses 1, 4 or 5 of that subsection – apply, the authority or entity requires the subcontractor to be replaced. Where the ground provided by subsection 4 of § 95 – or, in the fields of defence and security, the grounds provided by clauses 3 or 4 of that subsection, or by subsection 2 of § 177 – applies regarding the subcontractor, the authority or entity may require that the subcontractor be replaced. If the tenderer has been required to replace a subcontractor but does not do so, the authority or entity rejects the tender, unless the tenderer warrants that it will perform the relevant part of the contract itself.
(7¹) Where the contracting authority or entity, during procurement proceedings or during performance of the public contract, ascertains that, regarding a subcontractor, the grounds provided by clause 4 of subsection 1 of § 95 of this Act – or, where subsection 4¹ is applied, the ground provided by that subsection – apply, the authority or entity grants the subcontractor, through the tenderer, a period of at least three days to settle the tax debt or obtain a deferral. Where valid reasons are present, the authority or entity may extend the time limit. If the subcontractor has, by the due date set by the authority or entity, settled the tax debt or obtained a deferral, the authority or entity does not apply the provisions of subsection 7 of this section.
(8) In the case of a public works contract or works concession whose estimated value equals or exceeds the public procurement threshold, the contracting authority or entity, based on a request for information filed by a subcontractor who participated in the performance of the contract, presents to the subcontractor information on whether the tenderer has been remunerated for proven works performed by the subcontractor to the extent that the tenderer is required to remunerate the subcontractor. In the request, the subcontractor files with the authority or entity proof of existence of the sub-contract, the amount of the claim and whether the claim has fallen due. The authority or entity informs the tenderer without delay of the filing of the request and transmits a copy to the tenderer along with enclosed evidence and the information presented to the subcontractor.
(9) In the case of a public works contract or works concession whose estimated value equals or exceeds the public procurement threshold, where a subcontractor who participated in the performance of the contract or concession files with the contracting authority or entity a reasoned application in connection with groundless non-performance of a financial obligation by the tenderer under the subcontract concluded with the subcontractor, the authority or entity decides not to perform a corresponding part of the financial claim presented to it by the tenderer under the contract or concession. The authority or entity performs the financial obligation to the tenderer once the financial obligation to the subcontractor has been performed or evidence showing the subcontractor’s claim to be unfounded has been filed with the authority or entity.
(10) Non-performance of a financial obligation towards the tenderer based on an application of the subcontractor mentioned in subsection 9 of this section is not deemed a breach of the public contract by the contracting authority or entity.
(11) Where the contracting authority or entity provides for such possibility and relevant conditions in the procurement documents, the authority or entity may apply this section also in the case of:
1) public supply contracts;
2) public service contracts, where the services are not provided on site under the direct supervision of the authority or entity;
3) subcontracts concluded for the purchasing or delivery of supplies required for execution of works or provision of services;
4) subcontracts concluded by subcontractors.
Amended by RT I, 01.07.2017, 1 (in force from 1 January 2019) · RT I, 05.05.2022, 2 (in force from 1 June 2022) · RT I, 03.07.2026, 3 (in force from 1 November 2026)
On this site
Previous section
§ 121 — Voidness of a public contract
Next section
§ 123 — Modification of public contract