Skip to content

Public Procurement Act · Chapter 2

§ 115. Abnormally low tenders

Chapter 2 · Procurement Procedure · Division 4: Request to Participate and Tender · Subdivision 2: Tender

Changed 1 November 2026

Text of the consolidated version in force from 1 November 2026 (RT I, 03.07.2026, 7). Where this page and Riigi Teataja differ, Riigi Teataja prevails: official textOfficial English translation (it renders the version of 1 October 2026)The Estonian text is the only one with legal force; the English is a translation.

† Our own working translation of words that the reform of 1 November 2026 changed: Riigi Teataja has not yet published an official English text of them, and replaces ours when it does.

(1) Where the contracting authority or entity finds that the value of a tender is, given the subject matter of the public contract, unreasonably low, the authority or entity must, in a form reproducible in writing, require the tenderer to offer relevant clarifications and these must be given in the same form. The tenderer must submit a written explanation to the authority or entity within five working days following receipt of the corresponding requirement.

(1¹) In the case of a concession contract, the contracting authority or entity is not required to require the tenderer to provide the clarification mentioned in subsection 1 of this section, unless otherwise provided by the procurement documents.†

New from 1 November 2026

(2) In the case of a public works contract whose estimated value is at least 500 000 euros, the contracting authority or entity is required to require the tenderer whose tender it intends to declare successful to provide the clarification mentioned in subsection 1 of this section where at least three tenders have been submitted in the procurement procedure and the value of that tenderer’s tender is at least ten per cent lower than the value of the next tender or the value of that tenderer’s tender is at least 20 per cent lower than the average value of the tenders submitted.†

Changed 1 November 2026
Wording until 31 October 2026

In the case of a public works contract or a works concession whose estimated value equals or exceeds the public procurement threshold, the contracting authority or entity is required to require the tenderer whose tender it intends to declare suitable to provide the clarification mentioned in subsection 1 of this section where:

(2¹) The contracting authority or entity may, in a procurement document, state a percentage value that differs from the deviation provided for by subsection 2 of this section. The deviation provided for in a procurement document by reference to the tender that is next in terms of its value may amount to 5–15 per cent and by reference to the average value of the tenders, to 10–30 per cent. Where the authority or entity has not, in a procurement document, made provision for the special rule provided for by this subsection, the provision of subsection 2 of this section applies.†

Changed 1 November 2026
Wording until 31 October 2026

The contracting authority or entity may, in a procurement document, state a percentage value that differs from the deviation provided for by clause 1 of subsection 2 of this section. The deviation provided for in a procurement document by reference to the tender that is next in terms of its value may amount to 5–15 per cent and by reference to the average value of the tenders, to 10–30 per cent. Where the authority or entity has not, in a procurement document, made provision for the special rule provided for by this subsection, the provision of clause 1 of subsection 2 of this section applies.

(3) Repealed.

Repealed 1 November 2026
Wording until 31 October 2026

In order to identify the circumstances provided by clause 2 of subsection 2 of this section, the contracting authority or entity requires the tenderer to present, within a reasonable time limit set by the authority or entity, a certificate that has been issued by the competent authority of the country where the tenderer and any subcontractor named in the tender have their seat, which contains the following information:

(4) Repealed.

Repealed 1 November 2026
Wording until 31 October 2026

Where, for a reason beyond the control of the tenderer, they cannot offer the item of evidence mentioned in subsection 3 of this section, they may, for the purpose of establishing the circumstances provided for by clause 2 of subsection 2, offer other relevant evidence that allows the contracting authority or entity to decide whether to require clarifications. Where this is needed, the authority or entity may find evidence on its own.

(5) Repealed.

Repealed 1 November 2026
Wording until 31 October 2026

The contracting authority or entity does not require the offering of the item of evidence mentioned in subsection 3 of this section where the authority or entity has the corresponding information and it remains relevant for establishing the circumstances provided for by clause 2 of subsection 2.

(6) Repealed.

Repealed 1 November 2026
Wording until 31 October 2026

For the purpose of this section, the reference period is six calendar months the last of which is the calendar month preceding the calendar month preceding the calendar month of commencement of the public procurement. Where the tenderer or a subcontractor named in the tender was established or commenced business operations after the start of the reference period, the start of its reference period is the calendar month of establishment or commencement of business operations and the end of its reference period is the calendar month preceding the calendar month of commencement of the public procurement.

(7) The low value of a tender may be justified, above all, by the following:

1) the economics of the manufacturing process, of the services provided or of the construction method;

2) the technical solutions chosen by the tenderer or any exceptionally favourable conditions available to the tenderer for the performance of the public contract;

3) the originality of the supplies, services or works;

4) provisions governing the fields of environmental, social and labour law in the place of performance of the public contract, which the tenderer or the subcontractor must adhere to;

5) the possibility of the tenderer obtaining state aid.

(8) The contracting authority or entity verifies the clarification and assesses the evidence offered, consulting with the tenderer, where this is needed. Where the authority still finds that the value of the tender is abnormally low or where the tenderer offers no required clarifications to the authority or entity, the authority or entity rejects the tender by a reasoned written decision.

(9) Where the contracting authority or entity establishes that the abnormally low value of a tender is caused by disregarding provisions governing the fields of environmental, social and labour law in the place of performance of the public contract, the authority or entity rejects the tender.

(10) Where the contracting authority or entity establishes that the value of a tender is abnormally low because the tenderer has obtained state aid, the authority or entity may reject the tender only after the tenderer has been unable to prove, within a reasonable time limit set by the authority or entity, that the State aid granted to it was lawful. Where the authority or entity rejects the tender on such a ground and the estimated value of the public contract equals or exceeds the international threshold, the authority or entity notifies this to the European Commission through the Ministry of Finance.

The section as it read until 31 October 2026

(1) Where the contracting authority or entity finds that the value of a tender is, given the subject matter of the public contract, unreasonably low, the authority or entity must, in a form reproducible in writing, require the tenderer to offer relevant clarifications and these must be given in the same form. The tenderer must submit a written explanation to the authority or entity within five working days following receipt of the corresponding requirement.

(2) In the case of a public works contract or a works concession whose estimated value equals or exceeds the public procurement threshold, the contracting authority or entity is required to require the tenderer whose tender it intends to declare suitable to provide the clarification mentioned in subsection 1 of this section where:

1) in the procurement procedure, at least three tenders have been declared to be suitable and the value of the tender of the tenderer is at least 10 per cent lower than the value of next tender who has been declared suitable or the value of the tenderer’s tender is at least 20 per cent lower than the average value of the tenders that have been declared suitable, or

2) during the reference period, the average salary of the employees of the tenderer or of the subcontractors mentioned in its tender was less than 70 per cent of the average salary in the same period in the field corresponding to the subject matter of the contract.

(2¹) The contracting authority or entity may, in a procurement document, state a percentage value that differs from the deviation provided for by clause 1 of subsection 2 of this section. The deviation provided for in a procurement document by reference to the tender that is next in terms of its value may amount to 5–15 per cent and by reference to the average value of the tenders, to 10–30 per cent. Where the authority or entity has not, in a procurement document, made provision for the special rule provided for by this subsection, the provision of clause 1 of subsection 2 of this section applies.

(3) In order to identify the circumstances provided by clause 2 of subsection 2 of this section, the contracting authority or entity requires the tenderer to present, within a reasonable time limit set by the authority or entity, a certificate that has been issued by the competent authority of the country where the tenderer and any subcontractor named in the tender have their seat, which contains the following information:

1) the average salary paid by the tenderer during the reference period;

2) the average salary of each subcontractor named in the tender during the reference period;

3) the average salary during the reference period in the field corresponding to the subject matter of the public contract in the country where the tenderer and the subcontractor named in the tender have their seat.

(4) Where, for a reason beyond the control of the tenderer, they cannot offer the item of evidence mentioned in subsection 3 of this section, they may, for the purpose of establishing the circumstances provided for by clause 2 of subsection 2, offer other relevant evidence that allows the contracting authority or entity to decide whether to require clarifications. Where this is needed, the authority or entity may find evidence on its own.

(5) The contracting authority or entity does not require the offering of the item of evidence mentioned in subsection 3 of this section where the authority or entity has the corresponding information and it remains relevant for establishing the circumstances provided for by clause 2 of subsection 2.

(6) For the purpose of this section, the reference period is six calendar months the last of which is the calendar month preceding the calendar month preceding the calendar month of commencement of the public procurement. Where the tenderer or a subcontractor named in the tender was established or commenced business operations after the start of the reference period, the start of its reference period is the calendar month of establishment or commencement of business operations and the end of its reference period is the calendar month preceding the calendar month of commencement of the public procurement.

(7) The low value of a tender may be justified, above all, by the following:

1) the economics of the manufacturing process, of the services provided or of the construction method;

2) the technical solutions chosen by the tenderer or any exceptionally favourable conditions available to the tenderer for the performance of the public contract;

3) the originality of the supplies, services or works;

4) provisions governing the fields of environmental, social and labour law in the place of performance of the public contract, which the tenderer or the subcontractor must adhere to;

5) the possibility of the tenderer obtaining state aid.

(8) The contracting authority or entity verifies the clarification and assesses the evidence offered, consulting with the tenderer, where this is needed. Where the authority still finds that the value of the tender is abnormally low or where the tenderer offers no required clarifications to the authority or entity, the authority or entity rejects the tender by a reasoned written decision.

(9) Where the contracting authority or entity establishes that the abnormally low value of a tender is caused by disregarding provisions governing the fields of environmental, social and labour law in the place of performance of the public contract, the authority or entity rejects the tender.

(10) Where the contracting authority or entity establishes that the value of a tender is abnormally low because the tenderer has obtained state aid, the authority or entity may reject the tender only after the tenderer has been unable to prove, within a reasonable time limit set by the authority or entity, that the State aid granted to it was lawful. Where the authority or entity rejects the tender on such a ground and the estimated value of the public contract equals or exceeds the international threshold, the authority or entity notifies this to the European Commission through the Ministry of Finance.

Amended by RT I, 03.07.2026, 3 (in force from 1 November 2026)

Cross-references

Want your procurement documents checked before publication? We will show you how Procurelex Verifika does it.

Request a demo

General information on the Public Procurement Act in force. Not legal advice.