Text of the consolidated version in force from 1 November 2026 (RT I, 03.07.2026, 7). Where this page and Riigi Teataja differ, Riigi Teataja prevails: official textOfficial English translation (it renders the version of 1 October 2026)The Estonian text is the only one with legal force; the English is a translation.

(1) The contracting authority or entity does not return a tender security to the tenderer or calls it in where, as a result of the tenderer’s acts or omissions, the public contract is not awarded or the tenderer does not, within the time limit set by the authority or entity and for a reason due to the tenderer, commence performance of the contract that they have concluded by providing their acceptance.

(2) The contracting authority or entity may retain the tender security or call it in where the tenderer is not selected on the ground provided by subsection 5 of § 178 of this Act.

(3) Where the contracting authority or entity calls in or refuses to return the tender security, the authority or entity returns the security to the extent that it exceeds the harm suffered by the authority or entity.

(4) The contracting authority or entity returns a tender security to the tenderer within five working days following:

1) conclusion of the procurement procedure by virtue of clause 1 of subsection 3 of § 73 of this Act;

2) entry into effect of the decision concluding the procurement procedure under clause 2, 3, 4, 6 or 7 of subsection 3 of § 73 of this Act;

3) entry into effect of the decision mentioned in subsection 5 of § 96 of this Act or of the decision not to select mentioned in subsection 5 of § 98 or subsection 6 of § 104 or of the tender rejection decision mentioned in subsection 1 of § 114 or subsection 8 of § 115;

4) the expiry of the period of validity of the tender;

5) withdrawal of the tender in a situation provided for by subsection 3 of § 111 of this Act;

6) the decision to dismiss the tender under subsection 7 of § 111 of this Act.

(5) In situations set out in subsection 4 of this section, where the tender security is a guarantee, the contracting authority or entity informs the guarantor of waiving the rights arising from the guarantee.

Amended by RT I, 05.05.2022, 2 (in force from 1 June 2022)