Skip to content

Public Procurement Act · Chapter 2

§ 94. Time limits for submission of tenders and requests to participate in restricted procedure, competitive procedure with negotiation, innovation partnership and competitive dialogue

Chapter 2 · Procurement Procedure · Division 2: Fundamentals of Procurement Procedure · Subdivision 5: Time Limits for Submission of Tenders and Requests to Participate

Changed 1 November 2026

Text of the consolidated version in force from 1 November 2026 (RT I, 03.07.2026, 7). Where this page and Riigi Teataja differ, Riigi Teataja prevails: official textOfficial English translation (it renders the version of 1 October 2026)The Estonian text is the only one with legal force; the English is a translation.

† Our own working translation of words that the reform of 1 November 2026 changed: Riigi Teataja has not yet published an official English text of them, and replaces ours when it does.

(1) In a restricted procedure, competitive procedure with negotiation, innovation partnership and competitive dialogue, the time limit for submission of requests to participate must not be shorter than:

1) Repealed.

Repealed 1 November 2026
Wording until 31 October 2026

15 days from the filing of the contract notice with the register where the estimated value of the public procurement equals or exceeds the public procurement threshold, but is below the international threshold;

2) 30 days from the filing of the contract notice with the Publications Office.†

Changed 1 November 2026
Wording until 31 October 2026

30 days from the filing of the contract notice with the Publications Office where the estimated value of the public procurement equals or exceeds the international threshold.

(2) Where the register sends to the contracting authority or entity a notice of the elimination of deficiencies contained in the contract notice, the authority or entity sets a new time limit for submission of requests to participate, counting from the filing with the register of a contract notice, free of defects.

(3) In a restricted procedure, competitive procedure with negotiation, innovation partnership and competitive dialogue, the time limit for submission of tenders must not be shorter than:

1) Repealed.

Repealed 1 November 2026
Wording until 31 October 2026

15 days from the filing of the contract notice with the register, except in the case of a public works contract, where the estimated value of the public procurement equals or exceeds the public procurement threshold, but is below the international threshold;

2) Repealed.

Repealed 1 November 2026
Wording until 31 October 2026

25 days from the filing of the contract notice with the register in the case of a public works contract where the estimated value of the public procurement equals or exceeds the public procurement threshold but is below the international threshold;

3) 25 days from the issue of the invitation to tender where the entire communication and exchange of information takes place by electronic means;†

Changed 1 November 2026
Wording until 31 October 2026

25 days from the issue of the invitation to tender where the estimated value of the public procurement equals or exceeds the international threshold and the entire communication and exchange of information takes place by electronic means;

4) 30 days from the issue of the invitation to tender where the entire communication and exchange of information does not take place by electronic means.†

Changed 1 November 2026
Wording until 31 October 2026

30 days from the issue of the invitation to tender where the estimated value of the public procurement equals or exceeds the international threshold and the entire communication and exchange of information does not take place by electronic means.

(4) In a restricted procedure or a competitive procedure with negotiation, the contracting authority or entity may reduce the time limits mentioned in subsection 3 of this section to up to ten days in the case of a public contract for supplies or services or to up to 15 days in the case of a public works contract where:

1) the authority or entity has filed an indicative notice in accordance with the rules provided by subsection 3 of § 75 of this Act and the indicative notice contains the full mandatory information required in a contract notice, which was available at the time of filing the indicative notice, or

2) the authority or entity is unable to adhere to the minimum time limits for the submission of tenders due to urgent circumstances whose reasons are set out in the procurement documents.

(5) On the ground provided by clause 2 of subsection 4 of this section, the contracting authority or entity may reduce the time limit mentioned in clause 2 of subsection 1 to 15 days.

The section as it read until 31 October 2026

(1) In a restricted procedure, competitive procedure with negotiation, innovation partnership and competitive dialogue, the time limit for submission of requests to participate must not be shorter than:

1) 15 days from the filing of the contract notice with the register where the estimated value of the public procurement equals or exceeds the public procurement threshold, but is below the international threshold;

2) 30 days from the filing of the contract notice with the Publications Office where the estimated value of the public procurement equals or exceeds the international threshold.

(2) Where the register sends to the contracting authority or entity a notice of the elimination of deficiencies contained in the contract notice, the authority or entity sets a new time limit for submission of requests to participate, counting from the filing with the register of a contract notice, free of defects.

(3) In a restricted procedure, competitive procedure with negotiation, innovation partnership and competitive dialogue, the time limit for submission of tenders must not be shorter than:

1) 15 days from the filing of the contract notice with the register, except in the case of a public works contract, where the estimated value of the public procurement equals or exceeds the public procurement threshold, but is below the international threshold;

2) 25 days from the filing of the contract notice with the register in the case of a public works contract where the estimated value of the public procurement equals or exceeds the public procurement threshold but is below the international threshold;

3) 25 days from the issue of the invitation to tender where the estimated value of the public procurement equals or exceeds the international threshold and the entire communication and exchange of information takes place by electronic means;

4) 30 days from the issue of the invitation to tender where the estimated value of the public procurement equals or exceeds the international threshold and the entire communication and exchange of information does not take place by electronic means.

(4) In a restricted procedure or a competitive procedure with negotiation, the contracting authority or entity may reduce the time limits mentioned in subsection 3 of this section to up to ten days in the case of a public contract for supplies or services or to up to 15 days in the case of a public works contract where:

1) the authority or entity has filed an indicative notice in accordance with the rules provided by subsection 3 of § 75 of this Act and the indicative notice contains the full mandatory information required in a contract notice, which was available at the time of filing the indicative notice, or

2) the authority or entity is unable to adhere to the minimum time limits for the submission of tenders due to urgent circumstances whose reasons are set out in the procurement documents.

(5) On the ground provided by clause 2 of subsection 4 of this section, the contracting authority or entity may reduce the time limit mentioned in clause 2 of subsection 1 to 15 days.

Amended by RT I, 05.05.2022, 2 (in force from 1 June 2022) · RT I, 03.07.2026, 3 (in force from 1 November 2026)

Cross-references

This section refers to

Want your procurement documents checked before publication? We will show you how Procurelex Verifika does it.

Request a demo

General information on the Public Procurement Act in force. Not legal advice.