Public Procurement Act · Chapter 1
§ 46. Clarifications
Chapter 1 · General Provisions · Division 7: Rules Applicable to Communication and Requirements for Form of Documents
(1) The contracting authority or entity makes clarifications pertaining to procurement documents, or documents that allow for clarification, electronically available within three working days following receipt of a corresponding request for clarification. Where the entire public procurement communication and information exchange does not take place electronically, the authority or entity submits clarifications or documents allowing for clarification within the same time limit to all of the economic operators interested in the public procurement, which are known to the authority or entity, in a form reproducible in writing.
(2) Unless there is at least a six-day period between receipt, by the contracting authority or entity, of the request for clarification regarding procurement documents and the closing date for submission of tenders or, in situations mentioned in clause 2 of subsection 2 of § 93 and subsection 4 of § 94 of this Act, at least a four-day period or, in a simple procedure or a special procedure for social or other specific services, at least a two-day period, the authority or entity is not required to respond to the request for clarification.
(3) Clarifications or documents allowing for clarification submitted regarding procurement documents must not contain new information without which it is not possible to submit tenders or without which the submitted tenders would become non-compliant with the procurement documents or their content would change. It is prohibited to modify the procurement documents based on the clarifications and documents allowing for clarification.
(4) The economic operator submits to the contracting authority or entity clarifications or documents allowing for clarification regarding the inapplicability of grounds for exclusion, regarding information offered as proof of self-cleaning or of qualifications, or regarding information provided in the tender within three working days following receipt of the corresponding requirement from the authority or entity. Where a valid reason is present, the authority or entity may extend the time limit set to the operator for submission of documents or clarifications.
Amended by RT I, 05.05.2022, 2 (in force from 1 June 2022)