Public Procurement Act · Chapter 1
§ 34. Inclusion in the dynamic purchasing system
Chapter 1 · General Provisions · Division 6: Instruments of Public Procurement · Subdivision 2: Dynamic Purchasing System
(1) Throughout the period of operation of the dynamic purchasing system, the contracting authority or entity allows any economic operator to apply for inclusion in the system. Such applications may be submitted at any time.
(2) The contracting authority or entity finalises assessment of applications for inclusion in the dynamic purchasing system within ten working days following their receipt. The time limit may be prolonged to 15 working days in individual cases where justified, in particular because of the need to examine additional documentation or to otherwise verify whether the selection criteria are met.
(3) The contracting authority or entity may establish a time limit longer than the one mentioned in subsection 2 of this section for examination of applications for inclusion that are submitted within 30 days following publication of the contract notice.
Previous section
§ 33 — Setting up and closing a dynamic purchasing system
Next section
§ 35 — Award of public contract