# RHS § 93. Time limits for submission of tenders in open procedure

- URL: https://procurelex.ee/en/rhs/93 · Eesti: https://procurelex.ee/et/rhs/93
- Public Procurement Act (RHS), consolidated version in force from 2026-11-01 (RT I, 03.07.2026, 7); official text (prevails): https://www.riigiteataja.ee/akt/103072026007#para93
- Changed on 2026-11-01: the provisions that changed carry the words they replaced.
- † marks our own working translation of words the reform changed: Riigi Teataja has not yet published its English text of them. The Estonian text prevails.

(1) In an open procedure, the time limit for the submission of tenders must not be shorter than:
   1) Repealed.
      [repealed from 2026-11-01; until then: 15 days from the filing of the contract notice with the register, except in the case of a public works contract where the estimated value of the public procurement equals or exceeds the public procurement threshold but is below the international threshold and the entire communication and the entire exchange of information in the procurement procedure takes place by electronic means;]
   2) Repealed.
      [repealed from 2026-11-01; until then: 20 days from the filing of the contract notice with the register, except in the case of a public works contract where the estimated value of the public procurement equals or exceeds the public procurement threshold but is below the international threshold and the entire communication and the entire exchange of information in the procurement procedure does not take place by electronic means;]
   3) Repealed.
      [repealed from 2026-11-01; until then: 25 days from the filing of the contract notice with the register in the case of a public works contract where the estimated value of the public procurement equals or exceeds the public procurement threshold but is below the international threshold;]
   4) 30 days from the filing of the contract notice with the Publications Office, except in the case of a public works contract where the entire communication and exchange of information in the procurement procedure takes place by electronic means; †
      [changed on 2026-11-01; until then: 30 days from the filing of the contract notice with the Publications Office, except in the case of a public works contract where the estimated value of the public procurement equals or exceeds the international threshold and the entire communication and exchange of information in the procurement procedure takes place by electronic means;]
   5) 35 days from the filing of the contract notice with Publications Office, except in the case of a public works contract where the entire communication and exchange of information in the procurement procedure does not take place by electronic means; †
      [changed on 2026-11-01; until then: 35 days from the filing of the contract notice with Publications Office, except in the case of a public works contract where the estimated value of the public procurement equals or exceeds the international threshold and the entire communication and exchange of information in the procurement procedure does not take place by electronic means;]
   6) 45 days from the filing of the contract notice with the Publications Office in the case of a public works contract. †
      [changed on 2026-11-01; until then: 45 days from the filing of the contract notice with the Publications Office in the case of a public works contract where the estimated value of the public procurement equals or exceeds the public procurement threshold.]
(2) The contracting authority or entity may reduce the time limits mentioned in clauses 4 and 5 of subsection 1 of this section to 15 days and the time limit mentioned in clause 6 to 25 days where: †
   [changed on 2026-11-01; until then: The contracting authority or entity may reduce the time limits mentioned in clauses 2, 4 and 5 of subsection 1 of this section to 15 days and the time limit mentioned in clause 6 to 25 days where:]
   1) the authority or entity has filed an indicative notice in accordance with the rules provided by subsection 3 of § 75 of this Act and the indicative notice contains the entire mandatory information required in a contract notice, which was available at the time of filing the indicative notice, or
   2) the authority or entity is unable to adhere to the minimum time limits for submission of tenders due to urgent circumstances whose reasons are set out in the procurement documents.
(3) Where the register sends to the contracting authority or entity a notification concerning elimination of defects presented by the contract notice, the authority or entity sets a new time limit for submission of tenders counting the filing with the register of a contract notice, free of defects.