(1) The contracting authority or entity has a right to conduct a public procurement as a negotiated procedure without prior publication where:
   1) the restricted procedure, competitive procedure with negotiation or competitive dialogue has not yielded a single tender or request to participate, or where, by their nature, none of the tenders meet the conditions set out in the procurement documents and the needs of the authority or entity, and no substantial modification is made to the initial conditions of the procurement;
   2) the tenders submitted in the course of the restricted procedure, competitive procedure with negotiation or competitive dialogue do not meet the conditions set out in the procurement documents or where all of the requests to participate have been submitted by candidates who are to be, or may be, excluded based on clause 1, 4 or 5 of subsection 1 or on subsection 4 of § 95 of this Act or who do not meet the selection criteria, and no substantial modification is made to the initial conditions of the procurement;
   3) for technical reasons or reasons related to protection of exclusive rights, the public contract can be awarded only to a particular tenderer;
   4) the public contract involves air or maritime transport services for units of the Defence Forces, police or border guard operating or about to operate in a foreign country, which the authority or entity must purchase from economic operators the short validity period of whose tenders does not allow to comply with the time limits provided by § 94, by subsection 4 of § 125 or by § 174 of this Act;
   5) awarding the public contract in an expeditious manner is needed due to urgent need resulting from a crisis situation or to a situation of extreme urgency brought about by events unforeseeable to, and beyond the control of, the authority or entity, which does not allow to comply with the time limits provided by § 94, by subsection 4 of § 125 or by § 174 of this Act.
(2) On the ground mentioned in clause 2 of subsection 1 of this section, a public procurement may be conducted as a negotiated procedure without prior publication, provided that the procedure includes tenderers and candidates to whom the grounds for exclusion from the procurement procedure provided by this Act do not apply, who meet the established selection criteria and who, in the initial restricted procedure or competitive dialogue, have submitted a tender in the required form.
(2¹) Where this is required by the European Commission, the contracting authority or entity transmits, through the Ministry of Finance, to the Commission a report concerning the circumstances surrounding application of the ground provided by clause 1 of subsection 1 of this section.
(3) When awarding a public supply contract or a public service contract, the contracting authority or entity has a right to, in addition to the grounds provided by clause 1 of subsection 3 of § 49 of this Act and by subsection 1 of this section, conduct the public procurement as a negotiated procedure without prior publication if research and development services are purchased under the contract.
(4) When awarding a public supply contract, the contracting authority or entity has a right, in addition to the grounds provided by subsection 1 of this section, to conduct the public procurement as a negotiated procedure without prior publication on the grounds provided by clause 3 of subsection 3 and by subsection 4 of § 49 of this Act as well as where supplies are purchased from the same tenderer as a partial replacement for or an extension of previously purchased supplies and where switching the tenderer would oblige the authority or entity to purchase supplies which have different technical characteristics and which would not be technically compatible with existing supplies or whose operation and maintenance would entail disproportionate technical difficulties. The duration of such an additional contract may not extend five years, save for exceptional situations, having regard to the estimated service life of the products, equipment and systems as well as technical difficulties that switching the tenderer might entail.
(5) When awarding a public service contract or a public works contract, the contracting authority or entity has a right to, in addition to the grounds provided by subsection 1 of this section, carry out the public procurement as a negotiated procedure without prior publication where the following is to be purchased:
   1) additional works or services which were not included in the basic project or in the original contract but which have, through unforeseen circumstances, become necessary for the performance of the works or services described in that contract, to the extent of up to 50 per cent of the value of the contract, where such additional services or works cannot be technically or economically separated from the contract without major inconvenience to the authority or entity or when such services or works are strictly necessary for its completion;
   2) new services or works which consist in a repetition of similar services or works purchased from the same tenderer under a contract awarded as a result of a restricted procedure or a competitive procedure with negotiation and which are in conformity with the basic project up to five years earlier as a result of a restricted procedure or a competitive procedure with negotiation, provided that the initial contract notice states the possibility of such a contract being awarded and the estimated value of the initial public contract includes the total value of subsequent services or works.
(6) Under clause 2 of subsection 5 of this section, a public procurement may be conducted as a negotiated procedure without prior publication within five years following the award of the initial contract, save for exceptional situations, having regard to the estimated service life of the products, equipment and systems as well as technical difficulties that switching the tenderer might entail.