# RHS § 124. Termination of and withdrawal from public contract

- URL: https://procurelex.ee/en/rhs/124 · Eesti: https://procurelex.ee/et/rhs/124
- Public Procurement Act (RHS), consolidated version in force from 2026-11-01 (RT I, 03.07.2026, 7); official text (prevails): https://www.riigiteataja.ee/akt/103072026007#para124

(1) The contracting authority or entity has a right to terminate, or withdraw from, the public contract where:
   1) modifications not permitted under § 123 of this Act have been made to the public contract;
   2) a ground provided by clauses 1–4 of subsection 1 of § 95 of this Act applied to the economic operator at the time of award of the public contract and the operator should have been excluded from the procurement proceedings or should not have been awarded the contract, or
   2¹) during performance of the public contract, a ground provided by clauses 1–4 of subsection 1 of § 95 of this Act applies to the economic operator to whom the contract was awarded;
   3) the Court of Justice has established in proceedings based on Article 258 of the Treaty on the Functioning of the European Union that the obligations arising from the treaty or from Directive 2014/23/EU, 2014/24/EU or 2014/25/EU of the European Parliament and of the Council were breached in the public procurement or when awarding the public contract.
(1¹) The contracting authority or entity is required to terminate, or withdraw from, the public contract where:
   1) the economic operator to whom the contract was awarded is characterised – at the time of award or at any time following the award – by a ground provided by clause 5 of subsection 1 of § 95 of this Act or
   2) continuing to perform the public contract would violate an international sanction, or a sanction of the Government of the Republic within the meaning of the International Sanctions Act.
(1²) The contracting authority or entity notifies – in accordance with provisions of § 179¹ of this Act – any termination of or withdrawal from a public contract under subsection 1¹ of this section to the Financial Intelligence Unit.
(2) Where a public contract has been awarded by issuing the required acceptance, but the tenderer who received such acceptance does not commence performance of the public contract within the time set by the contracting authority or entity, the authority or entity may resort to early termination of the public contract or withdraw from the contract, and apply the rules provided by § 119 of this Act.