# RHS § 114. Verifying the suitability of tenders

- URL: https://procurelex.ee/en/rhs/114 · Eesti: https://procurelex.ee/et/rhs/114
- Public Procurement Act (RHS), consolidated version in force from 2026-11-01 (RT I, 03.07.2026, 7); official text (prevails): https://www.riigiteataja.ee/akt/103072026007#para114
- Changed on 2026-11-01: the provisions that changed carry the words they replaced.
- † marks our own working translation of words the reform changed: Riigi Teataja has not yet published its English text of them. The Estonian text prevails.

(1) The contracting authority or entity verifies whether the tenders submitted by tenderers or, in the case of the reverse procedure, the tenders opened before the selection of tenderers in accordance with the rules provided by § 113 meet the terms and conditions established in the procurement documents, and makes a reasoned written decision to declare the tenders suitable or to reject the tenders. A tenderer whose tender has been rejected cannot participate in the procurement procedure any further. †
   [changed on 2026-11-01; until then: The contracting authority or entity verifies whether the tenders submitted by tenderers or, in a situation provided for by subsection 3 of § 52 of this Act, the tenders opened before the selection of tenderers in accordance with the rules provided by § 113 meet the terms and conditions established in the procurement documents, and makes a reasoned written decision to declare the tenders suitable or to reject the tenders. A tenderer whose tender has been rejected cannot participate in the procurement procedure any further.]
(1¹) The contracting authority or entity may limit itself to verifying the conformity of only that tender which it intends to declare successful as a result of the assessment under § 117 of this Act (hereinafter full reverse procedure). In such a situation, the authority or entity ensures that the public contract is not awarded to a tenderer whose tender does not meet the terms and conditions set out in the procurement documents. The remaining tenderers continue to participate in the procedure. †
   [new from 2026-11-01]
(2) The contracting authority or entity rejects a tender where it does not meet the terms and conditions established in the procurement documents, the tenderer fails to provide clarifications by within the time limit required by the authority or entity or it is not possible to clearly assess whether the tender meets the terms and conditions established in the procurement documents. The authority or entity may declare a tender suitable where it does not contain any substantive deviations from the terms and conditions mentioned in the procurement documents.
(2¹) The contracting authority or entity rejects the tender if awarding the public contract based on that tender would violate an international sanction or a sanction imposed by the Government of the Republic within the meaning of the International Sanctions Act. The contracting authority or entity notifies – in accordance with provisions of § 179¹ of this Act – the Financial Intelligence Unit of the rejection.
(3) Where, in the technical specifications of the subject matter of the public contract, the contracting authority or entity has referred to a condition mentioned in subsection 2 of § 88 of this Act, the authority or entity does not reject a tender due to unsuitability if the tenderer proves in its tender by a method acceptable to the authority or entity by any relevant items of evidence that the solutions offered by the tenderer meet the requirements set out in the technical specifications.
(4) Where the contracting authority or entity has issued technical specifications of the subject matter of the public contract in accordance with the rules provided by subsection 1 of § 88 of this Act based on performance or functional requirements, the authority or entity does not reject a tender where the offered supplies, services or works meet some of the terms and conditions provided by subsection 2 which concern the performance or functional requirements that serve as the basis for the technical specifications and the tenderer proves it to the satisfaction of the authority or entity based on relevant evidence.
(5) Where the contracting authority or entity has established a condition mentioned in subsection 2 of § 89 of this Act in the technical specifications of the subject matter of the public contract, the authority or entity also accepts other equivalent labels as proof of conformity with the requirements of the label that has been named in the technical specifications.
(6) Where the contracting authority or entity has required that the tenderer provide a test report or a certificate issued by a conformity assessment body, the authority or entity also accepts, as proof of conformity with requirements, test reports or certificates issued by other equivalent conformity assessment bodies.
(7) Where, for objective reasons, the tenderer cannot obtain the label required by the contracting authority or entity or an equivalent label or a test report or a certificate issued by a specific conformity assessment body or by an equivalent conformity assessment body within the prescribed time limit, the authority or entity accepts other relevant evidence, provided that the tenderer proves to the satisfaction of the authority or entity that the offered supplies, services or works meet the requirements of the specific label or the requirements established by the authority or entity, unless the label, equivalent label or test report or another certificate of the specific conformity assessment body or equivalent conformity assessment body required by the authority or entity is the statutory prerequisite for the provision of the supplies, services or works on the market.
(8) Where the contracting authority or entity has divided the public procurement into lots within a single procedure, the authority or entity verifies the conformity of the tenders submitted regarding each lot with the terms and conditions of the procurement documents separately.
(9) Where the contracting authority or entity has divided the public procurement into lots within a single procedure and a tenderer has submitted a tender regarding more than one lot and its tender regarding at least one of the lots has not been rejected, the tenderer continues to participate in the procedure regarding these lots. †
   [changed on 2026-11-01; until then: Where the contracting authority or entity has divided the public procurement into lots within a single procedure and a tenderer has submitted a tender regarding more than one lot and its tender regarding any of the lots has been declared suitable, the tenderer continues to participate in the procedure regarding these lots.]
(10) Where a tenderer has submitted more than one tender or, in a public procurement that has been divided into lots within a single procedure, more than one tender regarding the same lot and at least one of the tenders submitted in the public procurement or tenders submitted regarding the lots has not been rejected, the tenderer continues to participate in the procedure with that tender or those tenders. †
   [changed on 2026-11-01; until then: Where a tenderer has submitted more than one tender or, in a public procurement that has been divided into lots within a single procedure, more than one tender regarding the same lot and any of the tenders submitted in the public procurement or tenders submitted regarding the lots have been declared suitable, the tenderer continues to participate in the procedure with its suitable tender or tenders.]