- Legal basis: § 185(1), § 185(2), § 185(4), § 185(5), § 186, § 189(1), § 189(2) cl 2, § 189(2) cl 3, § 189(4), § 189(4¹), § 189(5), § 189(6), § 189(7), § 189(8), § 189(9), § 189(10), § 120(2), § 125(9), § 194(2), § 201, § 194(4), § 194(5), § 194(9), § 193(1), § 193(2), § 193(9), § 193(8), § 193(5), § 193(6), § 197(1) cl 3, § 192(3) cl 5, § 200(1), § 197(1), § 198(1), § 198(3), § 200(4), § 200(6), § 201(1), § 201(2), § 201(3), § 201(3¹), § 120(4), § 121(1) cl 1, § 121(2), § 31(1), § 201(5), § 8(2), § 121(4), § 197(3), § 197(4), § 185(6)

Who may contest, within which periods, and what the contracting authority does when a contestation notice reaches it: the response, suspension, the decision of the Review Committee, the standstill period and the voidness of a contract.

## Who may contest, and what

A tenderer, candidate or [economic operator](https://procurelex.ee/en/glossary/economic-operator) interested in participating (the contesting party) may contest the actions of the contracting authority by filing a contestation notice with the Review Committee, if an infringement of the Act by the authority infringes its rights or adversely affects its interests ([§ 185(1)](https://procurelex.ee/en/rhs/185#lg1)). A notice may be filed against the procurement documents and against decisions such as exclusion, selection, rejection of a tender or declaring a tender successful ([§ 185(2)](https://procurelex.ee/en/rhs/185#lg2)). Some grounds concern the contract itself ([§ 185(4)](https://procurelex.ee/en/rhs/185#lg4)); several of them do not apply where the awarded contract is worth less than the simple procurement threshold ([§ 185(5)](https://procurelex.ee/en/rhs/185#lg5)). A statutory fee is paid on filing ([§ 186](https://procurelex.ee/en/rhs/186)).

## Time limits

The Act sets these periods for a notice to reach the Review Committee (see the [deadlines page](https://procurelex.ee/en/deadlines)). This guide repeats the wording of the Act and does not go into how periods are counted.

- General: ten days from the day the contesting party learned or should have learned of the infringement, but not after the contract is concluded ([§ 189(1)](https://procurelex.ee/en/rhs/189#lg1)).
- Procurement documents: at least five working days before the closing date, where the estimated value is at least the simple procurement threshold ([§ 189(2) cl 2](https://procurelex.ee/en/rhs/189#lg2-p2)); where time limits are shortened, ten days from making the document available electronically, but not after the closing date ([§ 189(2) cl 3](https://procurelex.ee/en/rhs/189#lg2-p3)).
- Simple procedure, and procurements below the simple procurement threshold: five working days ([§ 189(4)](https://procurelex.ee/en/rhs/189#lg4), [§ 189(4¹)](https://procurelex.ee/en/rhs/189#lg4-1)).
- Contract under a framework agreement: seven days ([§ 189(5)](https://procurelex.ee/en/rhs/189#lg5)).
- Optional notice: ten days from its publication in the register ([§ 189(6)](https://procurelex.ee/en/rhs/189#lg6)).
- Against the contract itself: 30 days from publication of the contract award notice ([§ 189(7)](https://procurelex.ee/en/rhs/189#lg7)); six months from conclusion where no notice was filed ([§ 189(8)](https://procurelex.ee/en/rhs/189#lg8)); 30 days from learning of the infringement where the rules on reopening competition under a framework agreement were breached ([§ 189(9)](https://procurelex.ee/en/rhs/189#lg9)).
- Compensation for harm: one year from conclusion of the contract ([§ 189(10)](https://procurelex.ee/en/rhs/189#lg10)).

The authority may not give its acceptance to the contract during the standstill period: 14 days ([§ 120(2)](https://procurelex.ee/en/rhs/120#lg2)), seven working days in the simple procedure ([§ 125(9)](https://procurelex.ee/en/rhs/125#lg9)).

## What the authority does when a notice is filed

- **Notification.** If there is no ground to dismiss the notice, the Review Committee informs the authority and sends it a copy ([§ 194(2)](https://procurelex.ee/en/rhs/194#lg2)). A contract concluded after the authority receives that notification and before the conditions of [§ 201](https://procurelex.ee/en/rhs/201) are met is void ([§ 194(4)](https://procurelex.ee/en/rhs/194#lg4)).
- **Response.** The authority files a written response within three working days of receiving the copy, with the documents the Committee requires, and may propose a way to resolve the notice ([§ 194(5)](https://procurelex.ee/en/rhs/194#lg5)). Further explanations are due within two working days of the Committee's request ([§ 194(9)](https://procurelex.ee/en/rhs/194#lg9)).
- **Suspension.** On the contesting party's reasoned application the Committee may suspend the procurement at any stage, deciding within three working days ([§ 193(1)](https://procurelex.ee/en/rhs/193#lg1), [§ 193(2)](https://procurelex.ee/en/rhs/193#lg2)). The authority notifies the known operators through the register without delay ([§ 193(9)](https://procurelex.ee/en/rhs/193#lg9)). If the closing date arrives during the suspension, it extends the time limit by a reasonable time and proposes that tenderers extend the validity of their tenders ([§ 193(8)](https://procurelex.ee/en/rhs/193#lg8)).
- **Permission to conclude.** Where the proceedings are the only obstacle to the contract and a significant public interest outweighs the harm to the contesting party, the Committee may, on the authority's reasoned application, permit the contract to be concluded; it considers the application within five working days ([§ 193(5)](https://procurelex.ee/en/rhs/193#lg5), [§ 193(6)](https://procurelex.ee/en/rhs/193#lg6)).
- **Ending it earlier.** The authority may recognise the notice as justified ([§ 197(1) cl 3](https://procurelex.ee/en/rhs/197#lg1-p3)). If it declares the procedure ineffective, revokes the contested decision or otherwise removes the infringement, the Committee dismisses the notice ([§ 192(3) cl 5](https://procurelex.ee/en/rhs/192#lg3-p5)).

## The decision and what follows

- **Decision.** The Committee decides the merits within 30 days of receiving a notice free of defects, or within 35 days if the notice was amended or supplemented ([§ 200(1)](https://procurelex.ee/en/rhs/200#lg1)). Proceedings end, among other ways, by settlement, withdrawal, recognition by the authority, a decision denying or granting the notice, or dismissal ([§ 197(1)](https://procurelex.ee/en/rhs/197#lg1)).
- **Costs.** Where the authority recognises the notice or it is granted in full, the authority pays the contesting party's statutory fee, expert fees and reasonable representative costs ([§ 198(1)](https://procurelex.ee/en/rhs/198#lg1)); where it is denied or withdrawn, the contesting party pays the authority's expert fees and reasonable representative costs ([§ 198(3)](https://procurelex.ee/en/rhs/198#lg3)).
- **Effect.** The decision enters into effect once the period for going to court has passed without a complaint ([§ 200(4)](https://procurelex.ee/en/rhs/200#lg4)). A decision granting the notice binds the authority ([§ 200(6)](https://procurelex.ee/en/rhs/200#lg6)).
- **Resuming and concluding.** The authority may not resume a suspended procurement or give its acceptance to the contract before 14 days have passed from the announcement of a decision denying or granting the notice ([§ 201(1)](https://procurelex.ee/en/rhs/201#lg1), [§ 201(2)](https://procurelex.ee/en/rhs/201#lg2)). After most other endings the period is seven days ([§ 201(3)](https://procurelex.ee/en/rhs/201#lg3)). After notice of an appeal, no acceptance may be given until the final court decision has entered into effect ([§ 201(3¹)](https://procurelex.ee/en/rhs/201#lg3-1)).

## When a contract is void

The Act makes a contract void in defined cases, for example when it is concluded before the standstill period has expired ([§ 120(4)](https://procurelex.ee/en/rhs/120#lg4)), without a required contract notice ([§ 121(1) cl 1](https://procurelex.ee/en/rhs/121#lg1-p1), subject to [§ 121(2)](https://procurelex.ee/en/rhs/121#lg2)), in breach of the rules on reopening competition under a framework agreement ([§ 31(1)](https://procurelex.ee/en/rhs/31#lg1)), contrary to a decision of the Review Committee ([§ 200(6)](https://procurelex.ee/en/rhs/200#lg6)) or in breach of the restrictions on resuming and concluding ([§ 201(5)](https://procurelex.ee/en/rhs/201#lg5)). A breach of the Act does not otherwise affect the validity of a contract ([§ 8(2)](https://procurelex.ee/en/rhs/8#lg2)), and voidness can be relied on only once established in accordance with the Act ([§ 121(4)](https://procurelex.ee/en/rhs/121#lg4)).

When it grants a notice against the contract itself, the Committee may declare the contract void or leave it in force while shortening its term, having regard to a significant public interest ([§ 197(3)](https://procurelex.ee/en/rhs/197#lg3)). Costs of delay, of a new procurement or of replacing the contractor are not such an interest, except where voidness would have disproportionate consequences ([§ 197(4)](https://procurelex.ee/en/rhs/197#lg4)). An economic operator that lost the contract because of an unlawful decision or procurement document may, after the contract is concluded, apply to the Committee for compensation for harm ([§ 185(6)](https://procurelex.ee/en/rhs/185#lg6)).

See also the [FAQ on contestation](https://procurelex.ee/en/faq/remedies).